Working project: Major repairs to the roof of a non-residential building at the address: Zhytomyr region, Berdychiv district, Andrushivka city, Kyivska st. 9


Sector
Education and science
Stream
Modernization of the infrastructure of educational institutions, including through the implementation of energy saving measures, and increasing the level of energy efficiency
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

Overhaul of the roof of a non-residential building at the address: Zhytomyr region, Berdychiv district, Andrushivka city, Kyivska st., 9. The existing children's creativity building is three-story, rectangular in plan. The project provides for a major roof repair: dismantling of the existing roof made of asbestos-cement corrugated sheets, major repair of damaged elements of the rafter system, installation of a metal roof, installation of a roof fence, snow guards, installation of a drainage system; lightning protection.

The purpose of the project

Main goal:

Creation of new jobs through project implementation

Secondary goal:

Creation of new facilities and services, Developing new territories or functions, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

It is planned: to provide appropriate conditions for the implementation of the educational process in the House of Children's Creativity by carrying out a major repair of the roof of the building. The implementation of the project is aimed at: - creating a safe environment for children and employees of the institution; - preventing further destruction of load-bearing structures and internal premises due to leaks; - preserving the building as an object of socio-cultural significance; - increasing the energy efficiency of the building by insulating and sealing the roof. The goal is to achieve this goal by performing a complex of construction and repair works, in particular: 1. Dismantling works: - dismantling the roof from asbestos-cement corrugated and metal galvanized sheets; - dismantling the crate; - dismantling the lightning rod pins; - dismantling the roofing felt; - dismantling the dormer windows; - dismantling the door blocks. 2. Arrangement of a hipped roof, which includes: - installation of elements of the rafter system; - execution of metal roofing on a wooden rafter system; - execution of organized drainage from the roof due to a suspended system of gutters; - arrangement of dormer windows and snow guards; - arrangement of a roof fence and transition bridges on the roof; - protection of wooden roof structures from rotting and combustion with the preparation DSA. 3. Execution of electric lighting of the roof and lightning protection of the roof.

Problems and solutions resulting from project implementation

Existing problems: 1. deterioration of the building's roof - numerous damages, leaks, which lead to leaks into the interior; 2. risks of destruction of structural elements - due to constant exposure to moisture, ceilings, walls and finishes suffer; 3. inadequate conditions for children and employees - a threat to safety, the appearance of fungus and dampness in the premises; 4. increased costs for building maintenance - increased heating costs due to heat loss and lack of high-quality waterproofing; Results of their solution after project implementation: 1. Restoration and reliable roofing - will provide protection of the building from precipitation and extend its service life; 2. Preservation of structural elements - prevention of further destruction of walls, ceilings and interior spaces; 3. Increasing the energy efficiency of the building - reducing heat loss and, as a result, saving budget funds for paying for utilities;

Socio-economic context

Indicator

Value

Capital expenditure per year

2050456 thous. UAH

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Modernization of the infrastructure of educational institutions, including through the implementation of energy saving measures, and increasing the level of energy efficiency

Strategic document

Стратегія розвитку територіальної громади

Task

Task 3.1.3 Conditions have been created for the safe stay of participants in the educational process, including persons with disabilities, in educational institutions of the urban territorial community.

Project objectives

Indicator
Base value
Target value
Creating safe and comfortable conditions for children and staff to stay indoors
0 %
100 %
Improving the energy efficiency of the building by restoring the thermal insulation properties of the roof and reducing heat loss
0 %
100 %
Promoting the development of extracurricular education through the creation of a modern and safe educational space for children
0 %
100 %

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Аналіз технічного стану об'єкту, нормативно - правове обгрунтування, соціально - економічний аналіз, фінансово - економічне обгрунтування, прогнозування майбутнього використання

Has data from external sources been used in the demand assessment?

Yes

Технічна документація та акти обстежень, нормативно-правові документи

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes

Враховані, оскільки кільткість дітей у громаді залишається стабільною та має тенденцію до зростання, це підтверджує сталу потребу у функціонуванні закладу позашкільної освіти. Економічні прогнози також враховано: у бюджеті громади передбачаються кошти на підтримку та розвиток освітньої інфраструктури.

Indicator
Year
Demand
Annual demand for services/infrastructure
1
100 %
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other gender risks
[Response was provided in the Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Economic analysis.pdf
24.09.2025
11:51:31 UTC

Alternative technical solutions

Technical Solution 1

Major repairs to the roof of a non-residential building at the address: Zhytomyr region, Berdychiv district, Andrushivka city, Kyivska st., 9

Technical Solution 2

Major repairs to the roof of a non-residential building at the address: Zhytomyr region, Berdychiv district, Andrushivka city, Kyivska st., 9

Total costs481'796 UAH666'296 UAH
  • For preparation
  • 102'500 UAH102'500 UAH
  • For implementation
  • 153'796 UAH153'796 UAH
  • For operation
  • 20'500 UAH205'000 UAH
  • For closing
  • 205'000 UAH205'000 UAH
    Average annual costs2'050'456 UAH2'050'456 UAH
    Project duration, incl.14 months14 months
  • Deadline for developing a FFS
  • 12 months12 months
  • Implementation period
  • 2 months2 months
    Service life1200 months1200 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget481'796 UAH666'296 UAH
    Capital costs481'796 UAH666'296 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation102'500 UAH102'500 UAH
    For implementation153'796 UAH153'796 UAH
    For operation20'500 UAH205'000 UAH
    For closing205'000 UAH205'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitвартість на одного отримувача послуги
    Service Unit Cost1'110 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    Yes, the project is suitable for PPP

    [Response was provided in the Investment Feasibility Study]

    km09q80z-0so7-4119-9829-b9k5f9825y90

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Investment Feasibility Study]

    Economic feasibility study - technical expertise

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    No, this is the first project of its kind.

    [Response was provided in the Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    Economic feasibility study - technical expertise

    [Response was provided in the Investment Feasibility Study]

    Зовнішня експертиза необхідна для підтвердження в попиті проєкту.

    Economic justification - social and gender analysis

    [Response was provided in the Investment Feasibility Study]

    Strategic justification - forming a justification for the problem and need

    [Response was provided in the Investment Feasibility Study]

    Management rationale - public consultation

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Investment Feasibility Study]

    Management rationale - project management

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - communication with stakeholders

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Investment Feasibility Study]

    Зовнішня експертиза необхідна для незалежної перевірки економічних розрахунків та підтвердження енфективності проекту.

    Management justification - other

    [Response was provided in the Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Investment Feasibility Study]

    Зовнішня експертиза необхідна для незалежної оцінки вартості проекту.

    Management rationale - risk management

    [Response was provided in the Investment Feasibility Study]

    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - working with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Зовнішня експертиза необхідна для залучення фінансових організацій (МФО) до проекту.

    Management justification - legal support

    [Response was provided in the Investment Feasibility Study]

    Зовнішня експертиза необхідна для незалежної компетенції та правомірності проекту.

    Is there an understanding of where to find relevant experts and consultants?
    Yes, negotiations are already underway.

    [Response was provided in the Investment Feasibility Study]

    Risk assessment

    Financial riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Other
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]