General information
Description of the project
The purpose of the project is to create a modern memorial space to honor the memory of the residents of the Storozhynets urban territorial community who died defending the independence, sovereignty and territorial integrity of Ukraine during the armed aggression of the Russian Federation.
The project involves the construction of a new memorial structure – «Stele of Heroes» in the city of Storozhynets, Chernivtsi district, Chernivtsi region. The project is aimed at creating a specially equipped place to honor the memory of the defenders within the city's recreational zone without demolishing existing buildings or communications.
Project objectives:
• Installation of a reinforced foundation slab to ensure the stability of the structure.
• Installation of a memorial stele (monument) made of natural granite stone.
• Execution of external decoration of the structure with granite slabs.
• Ensuring safe operation and inclusiveness of the facility (accessibility for people with reduced mobility).
• Carrying out work on the improvement of the surrounding area.
Expected results:
• Creation of a new architectural memorial object with a total built-up area of 69.6 m² and a maximum height of 2.45 m and completion of the compositional and architectural component.
• Arrangement of a public space for holding ceremonial events and commemorating the Heroes, which is important for the socio-patriotic context of the community.
• Improving the recreation infrastructure where the facility is located, in accordance with modern construction standards.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Reducing territorial or social gaps
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
1126 human
Number of users from low-mobility population groups
10580 human
Population in the geographical area of influence of the project
40682 human
Strategic Case
Strategic feasibility of the project
Sector
Social sector
Subsector
Veterans
Stream
Creating public spaces of diverse orientation
Strategic document
Стратегія розвитку територіальної громади
Task
3.5.1. Creation of public spaces of diverse orientation.
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Construction of the Heroes' Stele in Storozhynets, Chernivtsi region (correction)
Technical Solution 2
Preservation of the "Heroes' Stele" memorial complex in its current state without completing the construction of the third part
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]