New construction of a protective structure of the civil defense branch "Bobrovokutsky institution of general secondary education of the I-II degrees - preschool educational institution" of the Kaliniv support institution of general secondary education of the I-III degrees of the Berislav district of the Kherson region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project New construction of a protective structure for civil defense, branch "Bobrovokutsk secondary education institution of I-II levels - preschool educational institution" of the Kalynivka supporting institution of I-III levels of general secondary education of the Beryslav district of the Kherson region, was developed taking into account the requirements of urban planning documentation, initial data, technical conditions, design tasks and compliance with the requirements of the legislation, current building codes, state standards and rules, including accessibility requirements for the disabled and other low-mobility population groups, and provides for measures that ensure the safety of traffic and pedestrians.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Increasing compliance with modern standards, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDPs in the geographical area of impact of the project
258 human
Population in the geographical area of influence of the project
1568 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Ensuring the safety of the educational process
Strategic document
Strategy for the Development of the Civil Protection Shelter Fund until 2034
Task
Activity 8 of task 1 of the Operational Plan of Measures for the Implementation in 2025-2027 of the Strategy for the Development of the Fund of Civil Protection Protective Structures for the Period Until 2034 Providing educational institutions that provide complete general secondary education with civil defense protective structures to increase students' access to high-quality full-time education
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
New construction of a civil defense structure
Technical Solution 2
The easiest shelter
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]