Major renovation of the territory (street and road infrastructure facility) on Odessa Highway in the area of house No. 86 in the Central district of the city of Mykolaiv
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
It is necessary to carry out major repairs to the improvement of the territory with a total length of 58 m.p. Total area: asphalt concrete pavement 69 m2, sidewalk pavement 829.3 m2, installation of curbstone 249 m.p. Creation of a safe and accessible environment for pedestrians, a set of measures that make the space functional and aesthetic. Comfortable movement of residents, safe movement of low-mobility groups of the population and parents with wheelchairs, increasing the overall level of improvement of the settlement.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Increasing compliance with modern standards, Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Population in the geographical area of influence of the project
3000 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Restoration, development and modernization of street and road infrastructure facilities
Strategic document
Стратегія розвитку територіальної громади
Task
1.2.2 Improving infrastructure for pedestrians and cyclists, adhering to the principles of inclusion, accessibility, and mobility
Project objectives
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major renovation of the territory (street and road infrastructure facility)
Technical Solution 2
Current repairs of the territory's landscaping (street and road infrastructure facility)
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]