Construction of a storm sewer Du-1000 mm at the address: Odesa city, French Boulevard from Leontovycha Street to Akademichna Street
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
• To ensure stable operation and discharge of increasing
volumes of stormwater runoff it is necessary to construct a stormwater collector for 2026-2028. • improve and quality of maintenance of the stormwater sewer network;
(timely cleaning, removal of leaves/dust, cleaning of stormwater receiving parts);
• ensure uninterrupted passage of public transport through the city during heavy rainfall;
• Improvement of the operation of the existing stormwater sewer network;
• Expanding the coverage of territories for ensuring stormwater drainage;
• Improving the city's traffic during heavy rainfall. To resolve the issue of stormwater drainage on Frantsuzky Boulevard, it is necessary to build a stormwater collector Du 1000 mm long 2940 m from Leontovycha St. to Akademichna St.; The constructed collector along Frantsuzky Boulevard will provide stormwater drainage both on the roadway and adjacent streets, alleys and residential areas, which will ensure the safety of city electric transport, vehicles, pedestrians and will contribute to improving the sanitary condition of the territory of the recreational zone of the city of Odesa.
The purpose of the project
Main goal:
Improving the condition of infrastructure
Secondary goal:
Capacity building, Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Maintenance costs per year
1000 thous. UAH
Number of people who will use the service
1000 thous. people
Number of IDPs in the geographical area of impact of the project
133178 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Maintenance and repair of urban infrastructure facilities in good condition
Strategic document
State Strategy for Regional Development for 2021–2027
Task
10 Strengthening the financial capacity of local governments, creating conditions to ensure the implementation of their own and delegated powers by local governments.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Documents
Alternative technical solutions
Technical Solution 1
Construction of a storm sewer Du-1000 mm at the address: Odesa city, French Boulevard from Leontovycha Street to Akademichna Street
Technical Solution 2
Construction of a stormwater collector of 1000 mm diameter at the address: Odesa city, Frantsuzkyi Boulevard from Leontovycha Street to Akademichna Street with reinforcement of the road surface
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]