Reconstruction of the water supply from the 2nd lifting station to the 3rd lifting station at the address: Ukraine, Kyiv region, Fastiv district, Boyarsk urban territorial community


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Maturity level
78
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project to reconstruct the water supply from the II-th lifting station to the III-th lifting station in the Boyarska community involves the renewal of worn-out pipes and equipment to improve the reliability of water supply. The goal is to eliminate accidents, reduce water losses and unstable pressure, which will ensure a stable supply of high-quality drinking water to the community. The reconstruction will also increase the energy efficiency of pumping stations and improve the ecological condition of the region. It is expected that this will contribute to a better life for residents and sustainable development of the territory.

The purpose of the project

Main Goal:

Introducing innovations and energy-efficient solutions

Secondary Goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The goal of the water supply reconstruction project is to ensure a reliable and stable water supply for the Boyarska community by replacing worn-out pipes and upgrading pumping equipment. To achieve this goal, the pipe sleeve method is used to intervene without large-scale destruction of the existing infrastructure, which allows avoiding accidents and reducing repair costs. The gap between the current state and the target level is the significant wear of the network, loss of pressure, accidents and water shortages, which create risks for the quality and reliability of the community's water supply. The reconstruction will eliminate these problems and improve the quality of life of residents.

Problems and solutions resulting from project implementation

The key problems of the project are the breakdown and deterioration of the water supply, unstable pressure and inconsistent water supply, which creates risks for the quality and availability of drinking water. These problems are relevant due to the worn-out infrastructure, which causes frequent breakdowns and water waste. If not resolved, the population will face frequent interruptions, reduced sanitary standards and social inconvenience. The implementation of the project will ensure stable pressure, reduce breakdowns, improve water quality and raise the standard of living of residents, creating the prerequisites for sustainable development of the community.

Socio-economic context

Indicator

Value

Number of people who will use the service

90 %

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources

Strategic document

Стратегія розвитку територіальної громади

Task

2.3.1 Ensure proper functioning of existing water supply, drainage and heat supply facilities, taking into account modern energy-saving technologies

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Методологія оцінки попиту проєкту базується на аналізі технічного стану мережі, кількості споживачів і прогнозі потреб у воді. Збирають статистичні дані, опитують мешканців і підприємства, враховують вимоги до якості та обсягів водопостачання. Це дозволяє розрахувати обсяги реконструкції й оцінити вплив проєкту на стабільність і якість водопостачання в громаді.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
250000 m3
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis of the water supply.docx
22.10.2025
13:42:23 UTC

Alternative technical solutions

Technical Solution 1

Reconstruction of the water supply from the 2nd lifting station to the 3rd lifting station at the address: Ukraine, Kyiv region, Fastiv district, Boyarsk urban territorial community

Technical Solution 2

Using trenchless repair technologies, such as hydromechanical sleeving or threading new pipes into old ones without digging up the roadway.

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)32'020'000 UAH16'000'000 UAH
For preparation1'020'000 UAH1'000'000 UAH
For implementation31'000'000 UAH15'000'000 UAH
Project operation and closure cost2'980'000 UAH550'000 UAH
For operation2'730'000 UAH300'000 UAH
For closing250'000 UAH250'000 UAH
Average annual costs300'000 UAH0 UAH
Project duration, incl.24 months12 months
Deadline for developing a FFS12 months6 months
Implementation period12 months6 months
Service life300 months7 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget35'000'000 UAH16'550'000 UAH
Project cost (preparation and implementation)32'020'000 UAH16'000'000 UAH
For preparation1'020'000 UAH1'000'000 UAH
For implementation31'000'000 UAH15'000'000 UAH
Project operation and closure cost2'980'000 UAH550'000 UAH
For operation2'730'000 UAH300'000 UAH
For closing250'000 UAH250'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitДля розрахунку середньої вартості проєкту реконструкції водогону на одного отримувача послуги з урахуванням 25,000 жителів, загальна вартість проєкту (35,000,000 грн) ділиться на загальну кількість отримувачів протягом усього періоду експлуатації (25 років): Кількість отримувачів за весь період: 25000 × 25 = 625000 . Середня вартість на одного отримувача послуги за рік: 35000000/625000 ≈ 56 грн
Service Unit Cost56 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds33'985'240 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Yes, negotiations are already underway.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Technical riskDefinedUndefined
Economic riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
11/11/2025SP-L-111125-16DD6A24Community SPInvestment Feasibility StudyIncludeStrategic fit confirmed.-
23/03/2026SP-N-230326-2DB3812FState SPInvestment Feasibility StudyAwaiting review--
17/11/2025SPP-L-171125-A65CBAC2Community SPPInvestment Feasibility StudyIncludeStrategic fit confirmed78