New construction of a civil defense facility for the Municipal Clinical Hospital No. 1 of the Odessa City Council at the address: Odessa, Myasoyedovskaya St., 32
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The construction of a civil defense facility is planned on the territory of the hospital of the KNP "City Clinical Hospital No. 1" of the Odessa City Council at the address: Odessa, Myasoedovskaya St., 32. The facility is located in the Malinovsky administrative district of Odessa, in the historical center of the city with dense development - within the historical area of Odessa "Moldavanka", which is located in the "Complex of Jewish Hospital Buildings". The buildings of the surrounding development are two-story with load-bearing longitudinal and transverse walls made of limestone-shell stone and inserts made of ceramic brick, with wooden floors and pitched roofs.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
375 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Establishment of safe conditions in municipally owned healthcare facilities of the territorial community of Odessa, including the establishment of civil defense facilities
Strategic document
State Strategy for Regional Development for 2021–2027
Task
36 Ensuring the functioning of a capable public health system in regions and territorial communities.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
New construction of a civil defense facility for the Municipal Clinical Hospital No. 1 of the Odessa City Council at the address: Odessa, Myasoyedovskaya St., 32
Technical Solution 2
Construction of a modular civil defense facility for the Municipal Clinical Hospital No. 1 of the Odessa City Council at the address: Odessa, Myasoyedovskaya St., 32
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]