Creation of an educational and practical center for training young people in the subject "Defense of Ukraine"


Sector
Education and science
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the “New Ukrainian School” reform
Maturity level
63
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Regional level of SPP
Implementation
Completion

General information

Description of the project

Equipping a modern learning space to prepare young people for:

  • actions in emergency situations;
  • home medical care;
  • the foundations of national resistance;
  • working with modern technologies (drones).

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

Equipping a modern training space to prepare young people for: - emergency response; - first aid; - basics of national resistance; - working with modern technologies (drones).

Problems and solutions resulting from project implementation

The implementation of the project will allow creating a modern educational and practical center for training young people in the subject "Defense of Ukraine", which will ensure the acquisition of practical skills in first aid, actions in crisis situations, the basics of national resistance and the use of modern technologies. The project will contribute to increasing the level of security, practical training of young people and compliance of the educational process with modern challenges and state standards.

Socio-economic context

Indicator

Value

Number of IDP users

58 human

Number of employees of the institution/institution/organization

105 human

Number of people who will use the service

0.72 thous. people

Population in the geographical area of influence of the project

50 thous. people

Number of IDPs in the geographical area of impact of the project

0.65 thous. people

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the “New Ukrainian School” reform

Strategic document

Регіональна стратегія розвитку

Task

2.3.1. Improving the quality and territorial accessibility of educational services

Project objectives

Indicator
Base value
Target value
Creation of a training and practical center for professional education to train young people in the subject "Defense of Ukraine"
0 units
1 units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Оцінка попиту здійснювалась на основі аналізу кількості здобувачів освіти закладу, потреб освітнього процесу, наявної матеріально-технічної бази, а також потреб учнів навколишніх закладів освіти у сучасній практичній підготовці з предмета «Захист України».
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
26
322 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis of the project.pdf
15.05.2026
16:25:30 UTC

Alternative technical solutions

Technical Solution 1

Creation of a training and practical center for professional education to train young people in the subject "Defense of Ukraine"

Technical Solution 2

Modernization of existing classrooms without creating a separate training and practical center

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)3'300'000 UAH850'000 UAH
For preparation800'000 UAH50'000 UAH
For implementation2'500'000 UAH800'000 UAH
Project operation and closure cost500'000 UAH120'000 UAH
For operation300'000 UAH100'000 UAH
For closing200'000 UAH20'000 UAH
Average annual costs300'000 UAH0 UAH
Project duration, incl.24 months13 months
Deadline for developing a FFS6 months5 months
Implementation period18 months8 months
Service life180 months180 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget3'800'000 UAH970'000 UAH
Project cost (preparation and implementation)3'300'000 UAH850'000 UAH
For preparation800'000 UAH50'000 UAH
For implementation2'500'000 UAH800'000 UAH
Project operation and closure cost500'000 UAH120'000 UAH
For operation300'000 UAH100'000 UAH
For closing200'000 UAH20'000 UAH
Чи була під час уточнення орієнтовного бюджету використана Методика розрахунку вартості публічного інвестиційного проєкту, затверджена наказом Міністерства фінансів України №316 від 23.06.2025 р.?
Yes
[Response was provided in the Investment Feasibility Study]
Чи була під час розрахунку орієнтовного бюджету використана Методика розрахунку вартості публічного інвестиційного проєкту, затверджена наказом Міністерства фінансів України №316 від 23.06.2025 р.?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service Unit1 навчально практичний центр
Service Unit Cost2'000'000 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds2'000'000 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
No, this is the first project of its kind.

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Management justification - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Management rationale - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Is there an understanding of where to find relevant experts and consultants?
No, I need help.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Operational riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
15/05/2026SP-R-150526-052A820CRegional SPInvestment Feasibility StudyInclude--
19/05/2026SPP-R-190526-6EDE9F53Regional SPPInvestment Feasibility StudyInclude-63