Reconstruction of the sewer network from the "Silhosptehnika" microdistrict along Promyslovaya Street to the "Tsukrovykiv" microdistrict and KNS No. 6 in the city of Derazhnya, Khmelnytskyi region.
Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion
- Preparation
- General information
- Strategic Case
- Economic Case
- Financial Case
- Management Case
General information
Description of the project
The project involves replacing worn-out elements of the sewage system, which covers the entire western territory of the settlement. The main goals of the project are operational safety, proper engineering support, sanitary and epidemiological well-being of the population, environmental and technogenic safety, and energy saving.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
This project involves partial replacement of worn-out sewer pipes and wells, as well as the construction of STP No. 6.
Problems and solutions resulting from project implementation
This project will provide the population with reliable drainage, prevent accidents, promote sustainable development of the community, increase energy efficiency, reduce operating costs, optimize maintenance costs in the long term, prevent flooding, and improve the quality of life for community residents.
Socio-economic context
Indicator
Value
Number of IDP users
25 human
Number of people who will use the service
870 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Task
3 3.3.1. Development of documentation and support for projects to install a centralized water supply and wastewater system
Project objectives
Indicator
Base value
Target value
Reconstruction of gravity sewer network
340 m
852 m
Demand for the service and its dynamics
Indicator
Year
Demand
Annual demand for services/infrastructure
1
870 human
Economic justification
Alternative technical solutions
Technical Solution 1
Reconstruction of the sewer network from the "Silhosptechnika" microdistrict along Promyslovaya Street to the "Tsukrovykiv" microdistrict and KNS No. 6 in the city of Derazhnya, Khmelnytskyi region.
Technical Solution 2
New construction of a sewage network from the "Silhosptechnika" microdistrict along Promyslovaya Street to the "Tsukrovykiv" microdistrict and sewage treatment plant No. 6 in the city of Derazhnya, Khmelnytskyi region.
Total costs1'174'800 UAH2'247'000 UAH
Average annual costs300'000 UAH300'000 UAH
Project duration, incl.12 months13 months
Service life300 months300 months
Target indicatorsDefined Defined
Technical Solution Status
Active
Rejected
Components of a technical solution
Financial justification
Total project budget
Total preliminary budget1'174'800 UAH2'247'000 UAH
Capital costs1'174'800 UAH2'247'000 UAH
Operational costs0 UAH0 UAH
Preliminary cost breakdown
Operating costs for implementation0 UAH0 UAH
For preparation113'100 UAH150'000 UAH
For implementation986'700 UAH2'000'000 UAH
For operation60'000 UAH80'000 UAH
For closing15'000 UAH17'000 UAH
Average project cost per service recipient
Service UnitСередня вартість проєкту на одного отримувача послуги
Service Unit Cost54 UAH
Profitability of the project
Is the project expected to generate income?
ResponseNoNo
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo
Funding Sources
Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH
Management Rationale
Risk assessment
Financial riskDefinedUndefined
Results of the feasibility analysis
Economic Analysis
Social benefits and costs
Improving wastewater services
Environmental benefits and costs
Reducing the risk of contamination of the territory
Indirect benefits and costs
Loss reduction, energy saving