RECONSTRUCTION OF THE HEAT SUPPLY SYSTEM OF A RESIDENTIAL BUILDING AT THE ADDRESS: 7 CHERKASKA STREET IN THE SHEVCHENKIV DISTRICT OF KYIV
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Hot water supply to a residential building on Cherkasskaya Street, 7 is provided by gas columns. Heating is provided by a gas boiler room located in the basement of the building, which contradicts the Regulations on the operation of gas boiler rooms. In connection with the possible refusal of PJSC "KYIVGAZ" to supply gas to the boiler room due to violation of the above norms and rules, it is proposed to connect house No. 7 on Cherkasskaya Street to the networks of KP "KYIVTEPLOENERGO". Laying a new heating network will allow to eliminate the inefficient gas boiler room with outdated equipment and increase the reliability and quality of heat supply to consumers, reduce costs for repair work, preparation and heating of the coolant
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other economic
27385 thous. UAH
Other functional
128 m
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
District Heating
Stream
Розвиток об’єктів комунальної інфраструктури з використанням сучасних підходів і технологій
Strategic document
Стратегія розвитку територіальної громади
Task
1.3. Розвиток об’єктів комунальної інфраструктури з використанням сучасних підходів і техн
Project objectives
Project Sustainable Development Goals
Alternative technical solutions
Technical Solution 1
RECONSTRUCTION OF THE HEAT SUPPLY SYSTEM OF A RESIDENTIAL BUILDING AT THE ADDRESS: 7 CHERKASKA STREET IN THE SHEVCHENKIV DISTRICT OF KYIV
Technical Solution 2
Electric heating with storage
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]