Creating an educational space within the framework of the "New Ukrainian School" reform - Shchyretska TG


Sector
Education and science
Stream
Providing secondary education institutions of the Shchyretsk territorial community with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

Purchase of teaching aids and equipment, furniture, computer and multimedia equipment for the physical classroom (laboratory) of the Shchyretsk secondary education institution of grades I-III in the Lviv district of the Lviv region. To create a modern educational space, current repairs will be carried out and the necessary equipment will be purchased.

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

To ensure compliance of the educational process in educational institutions with the key principles and state standards of the New Ukrainian School (NUS), which will lead to a significant improvement in the quality of educational services and the formation of key competencies in students necessary for successful self-realization in the modern world. The goal is achieved through repairs and the purchase of equipment, namely the renovation of modern educational space, improving learning conditions and students' access to modern equipment, namely the lack of equipment that makes it impossible to ensure the educational process at the level of modern standards

Problems and solutions resulting from project implementation

The key problems that the project should solve are the outdated material and technical base of the physics classroom, the lack of modern equipment and an inclusive environment, which currently makes it impossible to implement the principles of the National School of Education and the formation of key competencies of students, and if not resolved will lead to a decrease in the quality of education and unequal opportunities, while the implementation of the project will ensure the creation of a modern educational space, increased motivation and the development of research skills.

Socio-economic context

Indicator

Value

Other social

1 units

Other social

106 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Providing secondary education institutions of the Shchyretsk territorial community with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform

Strategic document

Стратегія розвитку територіальної громади

Task

3.2.1 Updating the material and technical support of educational institutions

Project objectives

Indicator
Base value
Target value
number of classrooms that will be equipped
0 units
1 units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Оцінка попиту в проєкті для Щирецької громади здійснювалася комплексно — через техніко-економічне обґрунтування потреб закладу узгодження з цілями реформи «Нова українська школа», фінансово-економічний аналіз та офіційний моніторинг МОН
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
1 units
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
economic analysis of NUS_gymnasium (1) (1) (1).docx
16.04.2026
13:26:32 UTC

Alternative technical solutions

Technical Solution 1

Creating an educational space within the framework of the "New Ukrainian School" reform - Shchyretska TG

Technical Solution 2

Using mobile STEM kits as a primary resource

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)374'400 UAH300'000 UAH
For preparation0 UAH50'000 UAH
For implementation374'400 UAH250'000 UAH
Project operation and closure cost0 UAH70'000 UAH
For operation0 UAH50'000 UAH
For closing0 UAH20'000 UAH
Average annual costs80'000 UAH0 UAH
Project duration, incl.8 months4 months
Deadline for developing a FFS2 months2 months
Implementation period6 months2 months
Service life180 months60 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget374'400 UAH370'000 UAH
Project cost (preparation and implementation)374'400 UAH300'000 UAH
For preparation0 UAH50'000 UAH
For implementation374'400 UAH250'000 UAH
Project operation and closure cost0 UAH70'000 UAH
For operation0 UAH50'000 UAH
For closing0 UAH20'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitсередня вартість проєкту на одного отримувача послуг
Service Unit Cost3'532 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds374'400 UAH0 UAH
Expected Funds374'400 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
20/04/2026SP-L-200426-45158530Community SPInvestment Feasibility StudyInclude--
24/04/2026SPP-L-240426-525E6411Community SPPInvestment Feasibility StudyInclude--