Overhaul of storage facility No. 28861 (dual-purpose facility) of the building of the preschool educational institution "Zaporizhzhia Industrial Center for Vocational Education" at 2d Vyrobnychaya St., Zaporizhzhia


Sector
Education and science
Stream
Modernization of the infrastructure of vocational and specialized pre-higher education institutions
Maturity level
82
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

Major repairs to the shelter to eliminate wear and tear and create safe conditions that will ensure compliance with modern requirements for civil defense and the protection of participants in the educational process. 

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

Major repairs to the shelter to eliminate wear and tear and create safe conditions that will ensure compliance with modern civil defense requirements and the protection of participants in the educational process.

Problems and solutions resulting from project implementation

Socio-economic context

Indicator

Value

Number of people who will use the service

179 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

Professional education, specialized education

Stream

Modernization of the infrastructure of vocational and specialized pre-higher education institutions

Strategic document

Стратегія розвитку територіальної громади

Task

D.1.2 Formation of a single educational space of the city

Project objectives

Indicator
Base value
Target value
Creating an underground school with integrated shelter
0 human
179 human

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Оцінка попиту здійснювалася шляхом аналізу статистики учасників освітнього процесу, нормативних вимог до укриттів та консультацій з експертами, що підтвердило наявний розрив і обґрунтувало потребу в модернізації.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
179 human
Annual demand for services/infrastructure
2
179 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
EXP.REPORT No. 53302 dated 05.11.2025_Editorial_2.pdf
15.01.2026
14:18:12 UTC

Alternative technical solutions

Technical Solution 1

Shelter overhaul

Technical Solution 2

Construction of a separate shelter

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)16'492'843 UAH120'500'000 UAH
For preparation758'843 UAH500'000 UAH
For implementation15'734'000 UAH120'000'000 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Average annual costs1 UAH0 UAH
Project duration, incl.6 months11 months
Deadline for developing a FFS2 months3 months
Implementation period4 months8 months
Service life1200 months1200 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget16'492'845 UAH120'500'002 UAH
Project cost (preparation and implementation)16'492'843 UAH120'500'000 UAH
For preparation758'843 UAH500'000 UAH
For implementation15'734'000 UAH120'000'000 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitОсіб
Service Unit Cost87'899 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds8'770'266 UAH0 UAH
Expected Funds8'770'266 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
15/01/2026SP-L-150126-D9F8F02ACommunity SPInvestment Feasibility StudyCancellation of the decision to include in a joint venture--
16/01/2026SP-L-160126-7E58A681Community SPInvestment Feasibility StudyInclude--
20/01/2026SPP-L-200126-F2B1ECA0Community SPPInvestment Feasibility StudyInclude-82