General information
Description of the project
Project Goal: Improving access of students with special educational needs to quality educational and rehabilitation services in the Storozhynetsk community of Chernivtsi region in partnership by equipping educational institutions with specialized equipment and developing cross-border cooperation between teachers.
Problem / Need: In the border regions, there is insufficient development of educational infrastructure, limited access to modern digital tools and teaching methods. The lack of professional development of teachers, as well as social factors (parental migration, increased risk of dropout) negatively affect the quality of education of children, in particular students with special educational needs. Schools do not have sufficient resources for correctional and developmental work and support for vulnerable categories of children, exacerbated by the consequences of the war.
Project Objectives:
1. Modernization of infrastructure and equipment:
- Equipping the Storozhynetsky Lyceum with equipment for correctional and developmental classes (modular furniture, teaching materials, STEM sets, interactive whiteboard).
- Providing equipment for teacher assistants (laptops, printers, laminators).
- Creating barrier-free access (ramps).
- Creating an adaptive sports ground for children with special needs.
- Implementing digital speech therapy platforms (Timlogo, Cognitik).
2. Strengthening professional potential and cooperation:
- Conducting trainings and seminars for teachers (Tomatis method, working with digital platforms).
- Cross-border workshops and cultural and educational exchanges between Ukraine and Romania.
- Joint thematic events on inclusive education.
Expected results:
- Improved educational and inclusive environment in the lyceum.
- Providing children with SEN with special means for learning and correction.
- Improving the quality of correctional and developmental work and barrier-free.
- Increasing the professional capacity of teachers and assistants.
- Strengthening cross-border cooperation between Ukrainian and Romanian educational institutions.
- Achievement of targets: increasing the number of children using modernized conditions and providing 100% of children with SEN with assistive devices by 2028.
The purpose of the project
Main Goal:
Ensuring inclusiveness and equal opportunities
Secondary Goal:
Improving the equality of wealth distribution, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other functional
149 human
Other functional
42 human
Other functional
16 human
Other functional
845 human
Population in the geographical area of influence of the project
14077 human
Other social
40691 human
Number of IDPs in the geographical area of impact of the project
798 human
Other social
1126 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Purchase of teaching aids (special means of correction of psychophysical development) for children with special educational needs who are receiving complete secondary education
Strategic document
Стратегія розвитку територіальної громади
Task
3.4.1. Development of a network of educational and preschool institutions in the community
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Partnerships in education to support inclusive learning
Technical Solution 2
Maintaining the current state
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]