General information
Description of the project
The building is planned for the educational process for students of a lyceum with enhanced military-physical training in the Kharkiv region. Purpose: military-sports development center. The specified complex includes the following works: restoration and comprehensive repair of all damaged load-bearing structures of the building (walls, ceilings, etc.) and bringing them into full compliance with the requirements of current regulatory documents of Ukraine. Restoration of all damaged internal enclosing structures (partitions, fences, etc.), as well as entrance doors and interior doors with bringing the specified structures into full compliance with the requirements of current regulatory documents of Ukraine. Restoration of damaged interior decoration in the premises (floors, wall and ceiling decoration) of the building and bringing them into full compliance with the requirements of current regulatory documents of Ukraine. Restoration of the exterior decoration of the building facade. Restoration of the building roof. Restoration of porches. Restoration of the heating system with the implementation of measures to increase its energy efficiency and bring the heating system into full compliance with the requirements of DBN V.2.2-28:2010, DBN V.2.5-67:2013. Restoration of the ventilation system and bringing it into full compliance with the requirements of current regulatory documents of Ukraine. Restoration of the water supply system and bringing it into full compliance with the requirements of current regulatory documents of Ukraine. Restoration of the power supply system of the part and bringing it into full compliance with the requirements of current regulatory documents of Ukraine, including the implementation of measures to install modern power and protective equipment, use cable lines made of modern materials, in accordance with the requirements of DBN V.2.5-23:2010 and PUE-2017. Restoration of lightning protection and grounding systems and bringing them into compliance with the requirements of DSTU EN 62305-1:2012. Restoration of the electric lighting system and bringing it into full compliance with the requirements of current regulatory documents of Ukraine. Restoration of the fire alarm system and bringing it into full compliance with the requirements of current regulatory documents of Ukraine. Installation of video surveillance.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
320 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Modernization and reconstruction of the infrastructure of general secondary education institutions
Strategic document
Регіональна стратегія розвитку
Task
1.2.2. 1.2.5. 1.2.6. "Restoration of institutions and development of an accessible educational network, purchase of school buses. Providing educational institutions with modern computer equipment and the use of computer technologies in the educational process and promoting the development of digital literacy. Creating equal opportunities for personal development throughout life and creating conditions for national-patriotic education and civic education of the population."
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of non-residential premises of the DPY building of the Municipal Institution "Lyceum with Enhanced Military and Physical Training "Patriot"" of the Kharkiv Regional Council at the address: Kharkiv region, Chuguyiv district, Eskhar village, Gorky street, 13
Technical Solution 2
missing
[The technical approach was selected for further detailed analysis or implementation.]
[The project initiator has not taken any decision about this alternative technical approach.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]