- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The reconstruction and modernization of the Bereznehuvat Art School will provide modern after-school facilities that comply with safety and energy efficiency standards, improve the quality of after-school education, and create an incentive to attract and retain children in the community.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Rebuilding the damaged/destroyed, Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of employees of the institution/institution/organization
5 human
Number of people who will use the service
68 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
Extracurricular education
Stream
Creating conditions for obtaining quality education, ensuring the development and modernization of extracurricular education institutions
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.1 Ensure the quality, accessibility, safety, and inclusiveness of educational services and improve the material and technical base of educational institutions
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major renovation of the Bereznehuvat Art School
Technical Solution 2
Move the Bereznehuvat Art School to another community building
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]