"Reconstruction of the water supply system on Halytska Street in the village of Rozdil, Stryi district, Lviv region" Adjustment
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the reconstruction of the existing water supply network on Galitska Street in the village of Rozdil, Stryi district, Lviv region, in order to ensure reliable and uninterrupted water supply for residents of the settlement. The existing water supply networks are in unsatisfactory technical condition, have significant physical wear and tear, and are characterized by frequent emergency situations and water losses. This leads to water supply interruptions, a decrease in the quality of services, and additional costs for emergency repairs. Within the framework of the project, it is planned to dismantle worn sections of the water supply system, perform earthworks, lay new polyethylene pipelines of various diameters with a total length of about 1.3 km, install shut-off valves, fire hydrants, and construct water supply wells. It also provides for the laying of individual sections of the network using horizontal directional drilling, flushing and disinfection of pipelines, and after completion of the work — restoration of road surfaces, sidewalks and landscaping of the territory. The implementation of the project will increase the reliability of the water supply system, reduce water losses in networks, improve the quality of drinking water and ensure a stable water supply for residents of Halytska Street and adjacent areas. In addition, the installation of fire hydrants will contribute to increasing the level of fire safety in the settlement.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capacity
50 m3
Population in the geographical area of influence of the project
2251 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure
Strategic document
Стратегія розвитку територіальної громади
Task
2.4.1. Establish a water supply and drainage network.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the water supply system on Halytska Street in the village of Rozdil, Stryi district, Lviv region
Technical Solution 2
Current repair of the water supply system on Halytska Street in the village of Rozdil, Stryi district, Lviv region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]