Major road repairs on Zagorodky Street in the village of Shchyrets, Pustomyty district, Lviv region (Correction)
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
One of the most pressing problems that concerns residents of the Shchyrets United Territorial Community is the unsatisfactory, emergency condition of municipally owned roads. The problem of the quality of road repair is not new. In particular, the road surface of Zagorodki Street in the village of Shchyrets requires major repairs. However, this problem has not been solved for many years due to the lack of funds for the systematic repair of this road. It is expected that with the arrival of spring, the condition of the road will only worsen. The emergency condition of the road and the lack of high-quality road surface reduce the speed and comfort of movement, and lead to an increase in the cost of operating cars, and most importantly, negatively affect the safety of road traffic for both motorists and pedestrians.
The project provides for a set of measures designed to improve the transport and operational performance of the street by strengthening the existing road surface by aligning the longitudinal profile with the adjustment of the existing transverse profiles, improving the longitudinal drainage system and ensuring the organization of water drainage from the roadway. Water drainage from the roadway is provided by arranging a longitudinal and transverse slope, with subsequent drainage along the curb stone into the designed rainwater collectors, as well as into existing ditches through the designed water discharges. The project also provides for the installation of a reinforced concrete pipe Ø0.5m, L=12.5m at PC 0+62. Water drainage from the sidewalks is provided by arranging a transverse and longitudinal slope with subsequent drainage to the roadway of the street.
Overhaul is provided with the following characteristics:
- Design speed - 50 km/h;
- Road surface of the roadway and junctions - two-layer reinforced concrete coating with a thickness of 5 cm+5 cm;
- Road surface of the sidewalk - coating with FEM DSTU B EN 1338:2016 6 cm thick.
Construction length of the site - 1136 m.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other functional
1136 m
Population in the geographical area of influence of the project
6000 human
Strategic Case
Strategic feasibility of the project
Sector
Transport Sector
Subsector
Road transport and road infrastructure
Stream
Development and restoration of municipal road infrastructure for public use
Strategic document
Стратегія розвитку територіальної громади
Task
2.2.2. Reconstruction, major repairs and maintenance of municipal roads and sidewalks
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major road repairs on Zagorodki Street
Technical Solution 2
Carrying out annual current (pothole) road repairs on Zagorodky Street
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]