Major road repairs on Zagorodky Street in the village of Shchyrets, Pustomyty district, Lviv region (Correction)


Sector
Transport Sector
Stream
Development and restoration of municipal road infrastructure for public use
Maturity level
72
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

One of the most pressing problems that concerns residents of the Shchyrets United Territorial Community is the unsatisfactory, emergency condition of municipally owned roads. The problem of the quality of road repair is not new. In particular, the road surface of Zagorodki Street in the village of Shchyrets requires major repairs. However, this problem has not been solved for many years due to the lack of funds for the systematic repair of this road. It is expected that with the arrival of spring, the condition of the road will only worsen. The emergency condition of the road and the lack of high-quality road surface reduce the speed and comfort of movement, and lead to an increase in the cost of operating cars, and most importantly, negatively affect the safety of road traffic for both motorists and pedestrians. 

The project provides for a set of measures designed to improve the transport and operational performance of the street by strengthening the existing road surface by aligning the longitudinal profile with the adjustment of the existing transverse profiles, improving the longitudinal drainage system and ensuring the organization of water drainage from the roadway. Water drainage from the roadway is provided by arranging a longitudinal and transverse slope, with subsequent drainage along the curb stone into the designed rainwater collectors, as well as into existing ditches through the designed water discharges. The project also provides for the installation of a reinforced concrete pipe Ø0.5m, L=12.5m at PC 0+62. Water drainage from the sidewalks is provided by arranging a transverse and longitudinal slope with subsequent drainage to the roadway of the street.

Overhaul is provided with the following characteristics:

  • Design speed - 50 km/h;
  • Road surface of the roadway and junctions - two-layer reinforced concrete coating with a thickness of 5 cm+5 cm;
  • Road surface of the sidewalk - coating with FEM DSTU B EN 1338:2016 6 cm thick.
    Construction length of the site - 1136 m.

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The purpose of this project is to ensure quality standards of life and safety of the population of the Shchyrets territorial community and create conditions for increasing the level of investment attractiveness and economic development of the territory by improving the condition of the roadway of the road along Zagorodki Street in the village of Shchyrets. The project "Overhaul of the road along Zagorodki Street in the village of Shchyrets, Pustomyty District, Lviv Region (Correction)" provides for the repair of the road surface of a section of a communal road of a residential street in the village of Shchyrets with a total length of 1153.00 m, a width of the roadway of 6.0 m, a sidewalk width of up to 1.8 m, by arranging an asphalt concrete surface.

Problems and solutions resulting from project implementation

Currently, there is an urgent need to carry out major repairs to the road along Zagorodki Street in the village of Shchyrets, which will ensure the creation of favorable conditions for safe movement for both drivers and pedestrians, and improve the general level of improvement of the village territory. Every year, the condition of the road surface only worsens and is subject to new destruction and damage. In previous years, work was not carried out due to the lack of the necessary financial resources from the local budget, therefore, it is extremely important for the successful implementation of the project to attract funds from other sources. The implementation of the project will positively affect the satisfaction of the social needs of the population, improve the quality of life of residents of the Shchyrets community. It will also contribute to the attractiveness of the territory for attracting investments and activating economic activity. The commissioning of the specified facility will ensure the proper high-quality functioning of the pedestrian part of the sidewalks and the carriageway of the road along the street. Fences, which in turn will increase the level of safety and comfort of movement for both pedestrians and motorists, and reduce the level of traffic accidents on the road.

Socio-economic context

Indicator

Value

Other functional

1136 m

Population in the geographical area of influence of the project

6000 human

Strategic Case

Strategic feasibility of the project

Sector

Transport Sector

Subsector

Road transport and road infrastructure

Stream

Development and restoration of municipal road infrastructure for public use

Strategic document

Стратегія розвитку територіальної громади

Task

2.2.2. Reconstruction, major repairs and maintenance of municipal roads and sidewalks

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

При оцінці попиту враховувалися дані опитування мешканців Щирецької територіальної громади та аналізувалися дані експертів.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
365000 vehicles
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Calculation of the cost of the change project.pdf
13.02.2026
19:48:51 UTC

Alternative technical solutions

Technical Solution 1

Major road repairs on Zagorodki Street

Technical Solution 2

Carrying out annual current (pothole) road repairs on Zagorodky Street

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)33'632'184 UAH520'000 UAH
For preparation40'000 UAH20'000 UAH
For implementation33'592'184 UAH500'000 UAH
Project operation and closure cost60'000 UAH20'000 UAH
For operation60'000 UAH20'000 UAH
Average annual costs20'000 UAH0 UAH
Project duration, incl.12 months2 months
Deadline for developing a FFS6 months1 month
Implementation period6 months1 month
Service life120 months12 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget33'692'184 UAH540'000 UAH
Project cost (preparation and implementation)33'632'184 UAH520'000 UAH
For preparation40'000 UAH20'000 UAH
For implementation33'592'184 UAH500'000 UAH
Project operation and closure cost60'000 UAH20'000 UAH
For operation60'000 UAH20'000 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitВартість проєкту на 1 м будівельної довжини ділянки дороги
Service Unit Cost29'659 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds40'000 UAH0 UAH
Expected Funds40'000 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
13/02/2026SP-L-130226-0EB4A6A8Community SPInvestment Feasibility StudyInclude--
16/02/2026SPP-L-160226-4EC70E77Community SPPInvestment Feasibility StudyIncludeA decision was made to amend the community's EPP and include this project in the EPP.72