Major repairs of premises and storage room No. 89047 of the KNP “Cherkasy Regional Psychiatric Hospital of the Cherkasy Regional Council”, damaged as a result of military actions caused by the armed aggression of the Russian Federation, at the address Pavlova St., building 46, Smila, Cherkasy region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Restoration of the premises of the KNP “Cherkasy Regional Psychiatric Hospital of the Cherkasy Regional Council“, damaged as a result of military actions caused by the armed aggression of the Russian Federation“ and repair of storage No. 89047 to ensure the provision of high-quality and safe medical care to the patients of the institution, as well as the creation of working conditions for the staff of the institution. It is planned to carry out internal renovation works (in particular, the installation of sanitary facilities with toilets, washbasins, shower cabins, if possible, for each block/chamber; complete replacement of internal fittings; complete replacement of internal power supply, lighting, water supply and sewage networks within the premises being renovated and, if necessary, risers on all floors; - installation of fire alarms and video surveillance, etc.), ensuring barrier-free access, insulation of buildings, etc. The estimated number of patients and staff is 320 people.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Increasing compliance with modern standards, Rebuilding the damaged/destroyed, Improving the equality of wealth distribution, Improving the condition of infrastructure, Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Maintenance costs per year
134.2 mln UAH
Number of people who will use the service
337 human
Number of employees of the institution/institution/organization
465 workplaces
Number of users from low-mobility population groups
5 %
Population in the geographical area of influence of the project
1160700 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Rehabilitation, development and modernization of healthcare facilities
Strategic document
Регіональна стратегія розвитку
Task
3.3.3 Development and modernization of social infrastructure
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Major repairs of premises and storage room No. 89047 of the KNP “Cherkasy Regional Psychiatric Hospital of the Cherkasy Regional Council”, damaged as a result of military actions caused by the armed aggression of the Russian Federation, at the address Pavlova St., building 46, Smila, Cherkasy region
Technical Solution 2
Current repairs of premises and storage room No. 89047 of the KNP "Cherkasy Regional Psychiatric Hospital of the Cherkasy Regional Council", damaged as a result of military actions caused by the armed aggression of the Russian Federation, at the address Pavlova St., building 46, Smila, Cherkasy region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]