Reconstruction of the Palana Lyceum of the Palana Village Council of the Uman District of the Cherkasy Region on the street Hrushevskyi, 5, p. Palanka, Uman district, Cherkasy region, damaged as a result of military operations caused by the armed aggression of the Russian Federation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the reconstruction of the Palansky Lyceum of the Palansky Village Council of the Uman District, which was damaged as a result of military operations. The goal is to restore the building and create a safe, modern, energy-efficient and inclusive educational space for 480 users, including students, staff and IDPs. The works include the restoration of structures, modernization of engineering networks, insulation of facades, replacement of windows and doors, arrangement of shelters and landscaping of the territory, which will ensure a full-fledged educational process in full-time and mixed formats
The purpose of the project
Main Goal:
Rebuilding the damaged/destroyed
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Maintenance costs per year
1097241 UAH
Number of IDP users
25 human
Number of people who will use the service
480 human
Number of IDPs in the geographical area of impact of the project
471 human
Population in the geographical area of influence of the project
14507 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Restoration, development and modernization of secondary education institutions
Strategic document
Регіональна стратегія розвитку
Task
2.2.1. Introduction of innovative learning technologies in primary and secondary schools
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Reconstruction of the Palana Lyceum of the Palana Village Council of the Uman District of the Cherkasy Region on the street Hrushevskyi, 5, p. Palanka, Uman district, Cherkasy region, damaged as a result of military operations caused by the armed aggression of the Russian Federation
Technical Solution 2
Major repairs of the Palansky Lyceum of the Palansky Village Council of the Uman district of the Cherkasy region at 5 Hrushevskoho St., Palanka village, Uman district, Cherkasy region, damaged as a result of military actions caused by the armed aggression of the Russian Federation
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]