New construction of local treatment facilities on the territory of the Dubov Lyceum of the Dubov Village Council of the Kovel District of the Volyn Region in the village of Dubov on Prishkilna Street
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the construction of new local sewage treatment plants (LSTP) on the territory of the Dubov Lyceum of the Dubov Village Council of the Kovel District of the Volyn Region (Dubove Village, Pryshkilna St.).
Features and content of the project:
- The project plans to equip a modern system for collecting, discharging and treating domestic wastewater generated as a result of the activities of the educational institution.
- Installation of energy-efficient and environmentally safe local treatment plants that will ensure a high level of wastewater treatment to regulatory standards.
- The use of modern biological treatment technologies that do not require complex maintenance and minimize the negative impact on the environment is envisaged. After treatment, wastewater can be discharged into natural water bodies or reused for technical needs (for example, watering green areas).
Problems solved by the project:
- Lack of a proper wastewater treatment system on the territory of the lyceum.
- Potential contamination of groundwater and surface water near the educational institution.
- Non-compliance of existing conditions with sanitary and environmental standards.
Expected results of the project:
- Ensuring stable and effective treatment of all wastewater from the lyceum.
- Improving the sanitary and epidemiological condition of the territory and the conditions of stay of students and employees.
- Reducing the negative impact on the environment and increasing environmental safety communities.
- Creating a modern engineering infrastructure that will meet the requirements of sustainable development and environmental standards.
The purpose of the project
Main Goal:
Increasing the even distribution of resources
Secondary Goal:
Contribution to climate or environmental goals, Increasing compliance with modern standards, Introducing innovations and energy-efficient solutions, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
800 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Construction of wastewater treatment plants for community educational institutions
Strategic document
Стратегія розвитку територіальної громади
Task
A2.2. Construction of treatment facilities for the Dubivska Secondary School of I-III grades.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Construction of local wastewater treatment facilities on the territory of Dubovskogo Lyceum
Technical Solution 2
Biofiltration treatment plants (roll or modular biofilters)
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]