Reconstruction of the catering unit of the Lyuboml Lyceum No. 2 of the Lyuboml City Council, Kovel District, Volyn Region, at 16 Poshtova St., in the city of Lyuboml, Kovel District, Volyn Region


Sector
Education and science
Stream
Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)
Maturity level
79
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The reconstruction of the catering unit in an educational institution involves a complete renovation of the premises, engineering networks and the installation of modern equipment in accordance with the HACCP standards. This includes redevelopment to ensure the flow of processes, adherence to inclusivity, increased energy efficiency and aesthetic renovation of the dining hall.

 

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

During the project implementation, premises and engineering networks will be renovated, and combi-steam ovens, refrigeration equipment, modern stoves, and ventilation systems will be installed.

Problems and solutions resulting from project implementation

Abandoning outdated approaches to organizing student nutrition in secondary education institutions by introducing the latest technological processes, improving energy efficiency indicators, and adhering to the principles of the HACCP system in accordance with the School Nutrition Reform Strategy,

Socio-economic context

Indicator

Value

Number of people who will use the service

400 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)

Strategic document

Стратегія розвитку територіальної громади

Task

3.1 Formation of an integrated informational, educational, medical and cultural community space.

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Previous FEA for the food unit.docx
12.03.2026
15:06:28 UTC

Alternative technical solutions

Technical Solution 1

Reconstruct the catering unit of Lyuboml Lyceum No. 2 of the Lyuboml City Council, Kovel District, Volyn Region

Technical Solution 2

Do not reconstruct the catering unit of Lyuboml Lyceum No. 2 of the Lyuboml City Council, Kovel District, Volyn Region

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)27'350'000 UAH0 UAH
For preparation350'000 UAH0 UAH
For implementation27'000'000 UAH0 UAH
Project operation and closure cost58'000 UAH58'000 UAH
For operation58'000 UAH58'000 UAH
Average annual costs1 UAH0 UAH
Project duration, incl.16 months2 months
Deadline for developing a FFS4 months1 month
Implementation period12 months1 month
Service life120 months60 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget27'408'000 UAH58'000 UAH
Project cost (preparation and implementation)27'350'000 UAH0 UAH
For preparation350'000 UAH0 UAH
For implementation27'000'000 UAH0 UAH
Project operation and closure cost58'000 UAH58'000 UAH
For operation58'000 UAH58'000 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitНа кількість навчаємих
Service Unit Cost55'327 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Economic riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
12/03/2026SP-L-120326-E09E598BCommunity SPInvestment Feasibility StudyInclude--
16/03/2026SPP-L-160326-FC32D17BCommunity SPPInvestment Feasibility StudyIncludeminutes of the investment council dated 16.03.2026 No. 379