Reconstruction of the water supply from I. Bohuna St., along Myru St. to Budivelnykiv St. in the city of Derazhnya, Khmelnytskyi region
Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion
- Preparation
- General information
- Strategic Case
- Economic Case
- Financial Case
- Management Case
General information
Description of the project
The implementation of this project will provide residents of the eastern part of Derazhnya with high-quality water supply. It will reduce water losses, increase pressure, and improve energy efficiency.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Ensuring uninterrupted water supply to social facilities of the settlement, communal facilities and individual residential buildings of residents of the settlement. Prospects for the development of enterprises with significant water consumption. Improving fire safety conditions (installation of modern fire hydrants).
Problems and solutions resulting from project implementation
Emergency situations arise with significant water losses, increased electricity consumption (pipe bursts, failure of shut-off valves, unsatisfactory condition of wells). This project will provide solutions to them.
Socio-economic context
Indicator
Value
Number of IDPs in the geographical area of impact of the project
35 human
Population in the geographical area of influence of the project
1050 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Task
3 3.3.1. Development of documentation and support for projects to install a centralized water supply and wastewater system
Project objectives
Indicator
Base value
Target value
Fire hydrants
2 units
5 units
Number of consumers
780 human
1020 human
Demand for the service and its dynamics
Indicator
Year
Demand
Annual demand for services/infrastructure
1
760 human
Annual demand for services/infrastructure
2
774 human
Economic justification
Alternative technical solutions
Technical Solution 1
Reconstruction of the water supply from I. Bohuna St., along Myru St. to Budivelnykiv St. in the city of Derazhnya, Khmelnytskyi region.
Technical Solution 2
Partial replacement of worn parts of the water supply system from I. Bohun St., along Myru St. to Budivelnykiv St. in the city of Derazhnya, Khmelnytskyi region.
Total costs3'796'070 UAH850'000 UAH
Average annual costs124'000 UAH284'000 UAH
Project duration, incl.12 months10 months
Service life300 months36 months
Target indicatorsDefined Defined
Technical Solution Status
Active
Rejected
Components of a technical solution
Financial justification
Total project budget
Total preliminary budget3'796'070 UAH850'000 UAH
Capital costs3'796'070 UAH850'000 UAH
Operational costs0 UAH0 UAH
Preliminary cost breakdown
Operating costs for implementation0 UAH0 UAH
For preparation116'299 UAH150'000 UAH
For implementation3'617'808 UAH450'000 UAH
For operation48'703 UAH220'000 UAH
For closing13'260 UAH30'000 UAH
Average project cost per service recipient
Service UnitСередня вартість проєкту на одного отримувача послугиСередня вартість проєкту на одного отримувача послуги
Service Unit Cost149 UAH218 UAH
Profitability of the project
Is the project expected to generate income?
ResponseNoNo
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Source and MechanismYesNo
Funding Sources
Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH
Management Rationale
Risk assessment
Market riskDefinedUndefined
Results of the feasibility analysis
Economic Analysis
Social benefits and costs
Improving water services
Environmental benefits and costs
Providing high-quality water supply while preserving natural resources
Indirect benefits and costs
Loss reduction, energy saving