Reconstruction of the reception department of the building of the KNMP "Kremenchuk Intensive Care Hospital" at Pavlova Street, 2 in the city of Kremenchuk, Poltava region. Adjustments
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project involves the reconstruction of the reception department of the KNMP "Kremenchutska Intensive Care Hospital" at 2 Likariya Parnety (Pavlova) Street in Kremenchuk, Poltava Region, in order to create a modern emergency medical care department in accordance with current state building standards and a single national standard for the design of emergency medical care departments.
The project plans to reconstruct the existing premises on the first floor of the hospital building and build a special box for receiving emergency medical care vehicles, designed to simultaneously service two ambulances. After the reconstruction, the department will include all the necessary functional premises: waiting areas for patients, a registration office, patient triage rooms, examination rooms, an anti-shock ward, an operating room, a sanitary inspection room, diagnostic rooms (X-ray, tomography, ultrasound, FGDS), as well as office premises for medical personnel.
The purpose of the project
Main Goal:
Creation of new facilities and services
Secondary Goal:
Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the equality of wealth distribution, Ensuring inclusiveness and equal opportunities, Introducing innovations and energy-efficient solutions, Improving the quality of services, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capacity
300 human
Number of users from low-mobility population groups
100 human
Number of IDPs in the geographical area of impact of the project
31000 human
Population in the geographical area of influence of the project
218132 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring access to quality medical care through the development and modernization of medical infrastructure facilities
Strategic document
Strategy for the Development of the Healthcare System until 2030
Task
19 Strategic goal 1. Ensuring universal access of the population to quality medical services and tools for implementing the right to health Operational goal 4. Task. Ensuring a unified approach and determining priority criteria during the phased restoration of the healthcare system infrastructure, taking into account the needs of the population and its individual groups in order to restore access to medical services and taking into account plans for the development of capable networks of healthcare institutions
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the reception building
Technical Solution 2
Construction of a new reception building
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]