Reconstruction of the off-site water supply system of the city of Lozova, Kharkiv region, water mains D=600-1000mm, L1=33.128 km and L2=32.785 km. inventory No. 44055, 44056, 44057 and with an internal site pipeline
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
There are two existing main pipelines D=600-1000mm long L=33.128 and L=32.785km, pipe material – steel, reinforced concrete. The geographical difference in elevation between the bottom of the water main in Lozova at PK0 and the maximum water level in the RFV of Lozova is 56.7m. The average water consumption for 2024 is 4788 m/day. There are 4 branches on the water mains for connecting existing subscribers: Subscriber of the KP "Teplovodoservis" of the Lozova City Council (average daily consumption - 560.5 m/day): PK0+85 branch Ду=100mm nas.Elizavetivka PK 24 branch Ду=250mmna s-shche. Krasnopavlivka Subscriber "Lozovavodoservis" of the Lozova City Council (average daily consumption - 4227.5 m/day): PK250+13 branches DN=200mm, Lymanivka PK331+55 DN=700mm, entrance to the Lozova RFV
The purpose of the project
Main Goal:
Improving the quality of services
Secondary Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
100 thous. people
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Reconstruction, major repairs, new construction, restoration, development, modernization (including supply of equipment and materials) of facilities and networks of centralized water supply and wastewater disposal in Kharkiv, including with the introduction of alternative energy sources
Strategic document
Регіональна стратегія розвитку
Task
14 Availability of quality centralized water supply and wastewater services for different groups of citizens, taking into account the latest technologies and the needs of territorial communities.
Project objectives
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Reconstruction of the off-site water supply system of the city of Lozova, Kharkiv region, water mains D=600-1000mm, L1=33.128 km and L2=32.785 km. inventory No. 44055, 44056, 44057 and with an on-site pipeline
Technical Solution 2
Not provided
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]