Major repairs of sidewalks and intersections with the installation of barrier-free access to buildings and structures to ensure accessibility and safety of facilities for people with disabilities (measures to create a barrier-free space) on Volodymyr Kozak St. from Monastyrska St. to Vyacheslav Chornovol St. in the city of Poltava.
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
The project provides for major repairs of sidewalks and the intersection on Volodymyr Kozak Street from Monastyrska Street to Vyacheslav Chornovola Street, and the installation of elevated pedestrian crossings. In the remaining places where pedestrian sidewalks connect with the roadway at pedestrian crossings, the curbstone is lowered to the level of the roadway to allow movement of people with reduced mobility. The width of the sidewalk, its longitudinal and transverse slopes in accordance with the requirements of current regulatory documents, allow the movement of people with reduced mobility. To provide means of safety, orientation and information for people with visual impairments, the project provides for the installation of tactile accessibility elements in the areas where sidewalks are installed, which include tactile strips that contrast in color and texture from the surface on which they are installed. The use of warning and guiding tactile strips is envisaged.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Improving the equality of wealth distribution
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
5000 human
Number of IDP users
1000 human
Population in the geographical area of influence of the project
7000 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Road infrastructure restoration
Strategic document
State Strategy for Regional Development for 2021–2027
Task
2.1.2 Restoration and expansion of a network of high-quality public roads of local importance
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of sidewalks and intersections with the installation of barrier-free access to buildings and structures to ensure accessibility and safety of facilities for people with disabilities.
Technical Solution 2
Partial improvement of existing sidewalks and intersections.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]