General information
Description of the project
The pressure collector network consists of steel pipes, which, due to long-term operation (over 60 years), corrode, forming areas through which sewage flows to the surface. Wastewater generated by consumers in the city of Sokal and the village of Zhvyrka is supplied to the existing sewage treatment plants 1, 2, and 3 and is discharged from 2 along the existing branch of the pressure collector to the treatment facilities.
The project involves laying a pressure sewer collector along the existing route from 2 to the treatment facilities in the city of Sokal, 3.384 km long. The implementation of the project will ensure the stability of the city's centralized water drainage system, eliminate the risks of surges, reduce operating costs, and ensure environmental protection.
The purpose of the project
Main Goal:
Contribution to climate or environmental goals
Secondary Goal:
Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
23051 human
Capacity
10000 m3
Other functional
3384 m
Population in the geographical area of influence of the project
23985 human
Number of IDPs in the geographical area of impact of the project
1040 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Water supply and sanitation
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Strategic document
Стратегія розвитку територіальної громади
Task
2.1.4. Improving water supply and sanitation
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of sewage treatment plants in the city of Sokal, Lviv region, with a decrease in productivity to 10 thousand m3/day (adjustment). Phase 2
Technical Solution 2
Major overhaul of the pressure pipeline from KNS-2 to the treatment facilities in the city of Sokal
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]