Providing new fire-fighting equipment to the Rybakiv Lyceum of the Koblivka Village Council


Sector
Education and science
Stream
Construction and reconstruction and major repairs of buildings, including their roofs, communication systems, boiler rooms, equipment of state and municipal preschool, general education, and after-school educational institutions (fire-fighting equipment)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

Providing secondary education institutions with new fire-fighting equipment is necessary to protect the lives and health of students and staff, ensure safe evacuation, comply with fire safety regulations, and create appropriate and safe conditions for the educational process

Problems and solutions resulting from project implementation

Providing secondary education institutions with new fire-fighting equipment is necessary to protect the lives and health of students and staff, ensure safe evacuation, comply with fire safety regulations, and create appropriate and safe conditions for the educational process

Socio-economic context

Indicator

Value

Number of people who will use the service

202 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Construction and reconstruction and major repairs of buildings, including their roofs, communication systems, boiler rooms, equipment of state and municipal preschool, general education, and after-school educational institutions (fire-fighting equipment)

Strategic document

Стратегія розвитку територіальної громади

Task

2.6.2.3 Construction and reconstruction and major repairs of buildings, including their roofs, communication systems, boiler rooms, equipment of state and municipal preschool, general education, and after-school educational institutions

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other gender risks
[Response was provided in the Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
rationale.docx
09.11.2025
20:25:23 UTC

Alternative technical solutions

Technical Solution 1

Providing new fire-fighting equipment to the Rybakiv Lyceum of the Koblivka Village Council

Technical Solution 2

Provision of new fire-fighting equipment

Total costs75'000 UAH75'000 UAH
  • For preparation
  • 500 UAH500 UAH
  • For implementation
  • 73'000 UAH73'000 UAH
  • For operation
  • 1'000 UAH1'000 UAH
  • For closing
  • 500 UAH500 UAH
    Average annual costs15'000 UAH15'000 UAH
    Project duration, incl.2 months2 months
  • Deadline for developing a FFS
  • 1 month1 month
  • Implementation period
  • 1 month1 month
    Service life60 months60 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    No

    [Response was provided in the Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    No

    [Response was provided in the Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    No

    [Response was provided in the Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget75'000 UAH75'000 UAH
    Capital costs75'000 UAH75'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation500 UAH500 UAH
    For implementation73'000 UAH73'000 UAH
    For operation1'000 UAH1'000 UAH
    For closing500 UAH500 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitгривня
    Service Unit Cost371 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Investment Feasibility Study]

    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Other
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]