Improvement of settlements, namely: New construction of a pedestrian path with the arrangement of improvement elements (pedestrian path, bicycle path, etc.) from Colonel Gulyaev St. (Fontanka village), Ak. Zabolotnogo St. (Lisky village) to Academician Sakharov St. (Lisky village) Odessa district, Odessa region


Sector
Municipal infrastructure and services
Stream
Creating safe, inclusive movement through the community
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The lack of proper pedestrian and bicycle infrastructure between Fontanskaya TG and the city of Odesa creates risks for the safety of pedestrians and cyclists, particularly on roads with intensive traffic flow. The presence of pedestrian zones will help ensure safety and comfort for all road users.

The construction of a pedestrian and bicycle path between Fontanskaya TG and the city of Odessa will significantly improve conditions for pedestrians, cyclists and provide a convenient connection between these settlements.

Creating a safe and convenient infrastructure for pedestrians and cyclists by building a pedestrian path with landscaping elements and a bicycle path between Fontanskaya TG and the city of Odessa

The purpose of the project

Main goal:

Creation of new facilities and services

Secondary goal:

Increasing compliance with modern standards, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

Creating a safe and convenient infrastructure for pedestrians and cyclists by building a pedestrian path with landscaping elements and a bicycle path between Fontanskaya TG and the city of Odesa

Problems and solutions resulting from project implementation

The lack of proper pedestrian and bicycle infrastructure between Fontanskaya TG and Odessa creates risks for the safety of pedestrians and cyclists, particularly on roads with intensive traffic flow. The presence of pedestrian zones will help ensure safety and comfort for all road users. The construction of a pedestrian and bicycle path between Fontanskaya TG and Odessa will significantly improve conditions for pedestrians and cyclists and provide a convenient connection between these settlements.

Socio-economic context

Indicator

Value

Population in the geographical area of influence of the project

25544 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Urban planning and landscaping

Stream

Creating safe, inclusive movement through the community

Strategic document

Task

3.2.2. Ensure the development of pedestrian and bicycle infrastructure

Project objectives

Indicator
Base value
Target value

Demand for the service and its dynamics

Indicator
Year
Demand
Annual demand for services/infrastructure
1
5500 m
Economic justification

Alternative technical solutions

Technical Solution 1

It involves the construction of a pedestrian path and a bicycle path with the arrangement of all necessary elements of landscaping, ensuring the safety of pedestrians and cyclists.

Technical Solution 2

Minimal reconstruction - only a pedestrian path

Total costs23'270'000 UAH21'770'000 UAH
  • For preparation
  • 750'000 UAH750'000 UAH
  • For implementation
  • 20'000'000 UAH19'000'000 UAH
  • For operation
  • 2'500'000 UAH2'000'000 UAH
  • For closing
  • 20'000 UAH20'000 UAH
    Average annual costs20'000'000 UAH19'250'000 UAH
    Project duration, incl.15 months15 months
  • Deadline for developing a FFS
  • 3 months3 months
  • Implementation period
  • 12 months12 months
    Service life144 months144 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active
    Rejected
    Components of a technical solution
    To components
    0
    To components
    0

    Financial justification

    Total project budget

    Total preliminary budget23'270'000 UAH21'770'000 UAH
    Capital costs23'270'000 UAH21'770'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation750'000 UAH750'000 UAH
    For implementation20'000'000 UAH19'000'000 UAH
    For operation2'500'000 UAH2'000'000 UAH
    For closing20'000 UAH20'000 UAH

    Average project cost per service recipient

    Service Unitпослугапослуга
    Service Unit Cost23'270'000 UAH21'770'000 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesYes

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH
    Management Rationale

    Risk assessment

    Technical riskDefinedUndefined
    Results of the feasibility analysis
    Economic Analysis
    Social benefits and costs
    Benefits: Ensuring safe movement of pedestrians and cyclists; Improving accessibility of community areas for all population groups; Increasing the level of physical activity of residents, reducing the risk of road accidents; Creating a comfortable space for recreation and social contacts. Costs: Costs for construction and maintenance of paths and landscaping; Temporary inconvenience during construction work (noise, access restrictions).
    Environmental benefits and costs
    Benefits: Reduced use of short-distance motor vehicles, reduced CO₂ emissions; Greening the area, improving the urban microclimate; Supporting sustainable mobility and eco-infrastructure of the community. Costs: Temporary intervention in green areas during construction; Use of building materials that require control over environmental standards.
    Indirect benefits and costs
    Benefits: Increasing the attractiveness of the area for business and investors; Possible increase in the value of nearby real estate; Development of tourism and cycling culture; Strengthening the positive image of the community as innovative and comfortable for living. Costs: Additional administrative costs for project control and support; Possible attraction of additional financing for scaling the project.