Reconstruction of wastewater treatment facilities and construction of a technological line for the treatment and disposal of sludge at the Bortnytsia aeration station


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SPP
Implementation
Completion

General information

Description of the project

BORTNYTSKY AERATION STATION (hereinafter – The wastewater treatment scheme is identical at each unit of the treatment facilities. The sludge formed during the wastewater treatment process is subject to processing in order to reduce its volume and disinfect it. Sludge processing takes place in special facilities - methane tanks and aerobic stabilizers. After processing, the sludge is pumped to sludge fields for further drying in natural conditions. The existing sludge fields occupy a total area of over 272 hectares. When designing the BSA, the volume of sludge in the sludge fields was predicted at 3.5 million m3. But in fact, they are three times overfilled. More than 10 million m3 of sludge has accumulated in three sludge fields and its amount is growing every day. Due to their overfilling, there is a constant threat of sludge spillage, flooding of nearby territories, and pollution of water resources. The Bortnytsia Aeration Station Modernization Project provides for reconstruction in 2 stages with the allocation of 5 start-up complexes in each stage. Considering that the construction of new structures, reconstruction and dismantling of existing ones is carried out at an enterprise operating in a continuous technological process, the following was determined as a priority: - the order of removal of individual structures subject to reconstruction from the technological process, compliance with which will ensure the normal operability of the treatment facilities; - the sequence of construction of new structures and dismantling of existing ones, ensuring the operability of the treatment facilities, is determined; - to outline (territorially) zones of construction and reconstruction in such a way as to fully ensure the movement of both construction and technological transport; During the preparatory period, the following works are also being carried out: - installation of temporary buildings and structures; - connection to sources of energy and water supply; - dismantling (demolition) of structures that are out of operation during the reconstruction; - demolition of green spaces located in the development zone; - measures to organize traffic safety during the construction period; - measures to organize the drainage of rainwater from mountainous areas. The construction is provided with water from the section of the water supply pipeline laid during the preparatory period. Source of temporary power supply - 110/6 kV substation "Lugova", 110/35/6 kV substation "Bortnychi". During the period of rehabilitation of pressure pipelines and reconstruction of the dispersive outlet, drinking water is transported by tankers, source of temporary power supply - 110/6 kV substation "Lugova", 110/35/6 kV substation "Bortnychi". Construction of structures below the groundwater level will be carried out under the protection of construction water lowering. Taking into account the geological structure of the site, hydrogeological characteristics of the soils, and the adopted methods of work, the most effective and cost-effective method of lowering the groundwater level will be water lowering using needle filter installations. Construction phase 1 includes: Start-up complex 1. Technical re-equipment of the structures of the 2nd and 3rd units in order to ensure regulatory treatment of the entire volume of wastewater for the period of construction of the new 1st unit with the installation of an air deodorization system from the block structures. Start-up complex 2. Construction of a mechanical wastewater sludge dewatering shop. Start-up complex 3. Construction of a new technological line for wastewater sludge utilization. Start-up complex 4. Construction of the new 1st unit Start-up complex 5 Preparatory work carried out: preparation of the territory, construction of new buildings and structures. As part of the preparatory work, pioneer sludge fields were liberated, work was carried out on vertical planning of the territory liberated from "pioneer" sludge fields and beyond them to the design marks, and sediment from "pioneer" sludge fields was transported. The second stage of construction includes: Launching complex 6. Reconstruction of the "Poznyaki" sewage station with the installation of an air deodorization system. Launching complex 7. Reconstruction of the "Pravoberezhnya" sewage station with the installation of an air deodorization system. Launching complex 8. Construction of a new II unit. Launching complex 9. Reconstruction of the structures of III unit of the station Launching complex 10. Reconstruction of the main channel of treated wastewater and dispersive discharges. Construction of a car farm and repair shops Wastewater treatment process When selecting a suitable wastewater treatment process, it was found that the most suitable option would be an aerobic-anoxic-oxygen process (A2O), which is carried out using an endless tray type, this alternative was also approved during the development of project documentation. In addition to phosphorus removal, additional treatment facilities are installed as a supplement to meet the requirements for phosphorus waste. A high-level coagulation tank will be added to achieve the above-mentioned goal. The choice was made based on the characteristics of the wastewater entering the treatment, as well as the wastewater flow rate entering the BSA, meeting the requirements for economic feasibility and ease of operation. The wastewater treatment process consists of a pre-treatment and primary treatment process to remove sand and mechanical impurities from the incoming wastewater, followed by a biological treatment process consisting of biological reactors (aerotanks), secondary settling tanks and disinfection using ultraviolet lamps, as well as a post-treatment process to ensure the removal of nutrients and compliance with the strict requirements in force in Kyiv. The project provides for the following sequence of the technological process for water treatment: 1. Coarse and fine screens, grease and sand traps, primary settling tanks located in one building to prevent the spread of odor. 2. Biological removal of nitrogen and phosphorus using the anaerobic-anoxic-aerobic process. 3. Secondary settling tanks. 4. Post-treatment of wastewater to remove fine suspended particles and dephosphorization of these substances. 5. Disinfection of treated wastewater with ultraviolet radiation. The sequence of the technological process for sludge treatment: 1. Gravity and mechanical thickening of sludge. 2. Mechanical dewatering of sludge 3. Thermal utilization of dewatered sludge. The BSA reconstruction project provides for the introduction of Japanese technologies for sludge treatment and utilization, which will ensure a significant reduction in its volume. Gravity and mechanical compactors are designed to reduce the volume and moisture of the sludge. At the next stage, the dewatered sewage sludge is transported to innovative sludge incinerators for thermal utilization. The combustion technology is so advanced that it almost does not use natural gas to support the combustion process. The flue gases generated during the operation of the sludge incinerators are cleaned in a wet scrubber to achieve minimal emissions of pollutants. The equipment to be installed during the Project will increase efficiency, reduce energy use and minimize negative impacts on the environment. The final product of sewage sludge utilization will be ash, which can be used in industry. Buildings and equipment that are a source of unpleasant odors are covered and have independent ventilation. According to the Project, air purification is carried out by the following methods: passing polluted air through activated carbon filters or feeding it to sludge incinerators for subsequent combustion. Construction period – 6 years.

The purpose of the project

Main goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The purpose of the project is to reconstruct the existing Units No. 2, 3 of the treatment plants and construct a new Unit 1. New buildings for mechanical wastewater treatment will be built for each unit of the station, they will include two-stage treatment on mechanized grates, sand traps, grease traps and primary clarifiers within the same building. Reconstruction of aeration tanks of Units 2 and 3 is planned, and for Unit 1 new aeration tanks will be built for full biological wastewater treatment with the creation of nitrification and denitrification zones in them. The technology of wastewater treatment of Unit 1 will allow reducing the concentration of phosphorus in accordance with the requirements of European directives. Before discharge to a water body, the treated wastewater is disinfected with ultraviolet radiation. The latest domestic and world standards were taken into account when developing the project for the reconstruction of the Bortnytsia aeration station. The quality of treated wastewater will be monitored in the future according to 10 indicators, and the design capacity of the plant will be 1,573,000 m3 per day. 1. Wastewater treatment in accordance with the requirements of Council Directive 91/271/EEC "On urban waste water treatment". 2. Disposal of sediment and sludge instead of accumulation in sludge fields. 3. Solving the problem of unpleasant odors in order to reduce the negative impact on the environment and create better working conditions for employees of the Bortnytsia aeration plant.

Problems and solutions resulting from project implementation

The equipment to be installed during the Project implementation will increase efficiency, reduce energy use and minimize negative impacts on the environment. The final product of the sewage sludge disposal will be ash, which can be used in industry. Buildings and equipment that are a source of unpleasant odors are covered and have independent ventilation. According to the Project, air purification is carried out by the following methods: passing polluted air through activated carbon filters or feeding it to sludge incinerators for subsequent combustion

Socio-economic context

Indicator

Value

Number of people who will use the service

4.2 mln people

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Restoration, development and modernization of centralized water supply and wastewater infrastructure, including the introduction of alternative energy sources

Strategic document

State Strategy for Regional Development for 2021–2027

Task

Task 14 under the “Comfortable Communities” area of Operational Objective 1. Infrastructure resilient to security, social and economic challenges Availability of quality centralized water supply and wastewater services for different groups of citizens, taking into account the latest technologies and the needs of territorial communities

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Фоктичні дані ПрАТ АК Київводоканал

Has data from external sources been used in the demand assessment?

No

Does the demand forecast take into account the latest demographic and economic forecasts?

No
Indicator
Year
Demand
Annual demand for services/infrastructure
1
100 %
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро

Climate change adaptation
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро

Pollution prevention and control
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Pollution prevention and control
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Climate change adaptation
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Покращення екологічного стану річки Дніпро, зниження рівня забруднення

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?

No
[Response was provided in the Investment Feasibility Study]

Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?

Yes, it was conducted
[Response was provided in the Investment Feasibility Study]

Реєстраційний номер справи 201811222220

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other gender risks
[Response was provided in the Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Investment Feasibility Study]

Were consultations held with representatives of target groups to take into account gender equality issues in the project?

Focus groups or consultations with women and vulnerable groups were held
[Response was provided in the Investment Feasibility Study]
Feedback on the project design was received from organizations working with women
[Response was provided in the Investment Feasibility Study]
No consultations were held with target groups.
[Response was provided in the Investment Feasibility Study]
Women's participation is ensured at various stages of planning (including public hearings)
[Response was provided in the Investment Feasibility Study]

Have the gender risks and social impacts of the project been assessed?

All possible positive impacts of the project on women, men or other gender groups have been identified
[Response was provided in the Investment Feasibility Study]
A plan to mitigate negative social impacts focused on women has been developed
[Response was provided in the Investment Feasibility Study]
The percentage of women who could be resettled has been quantified
[Response was provided in the Investment Feasibility Study]
The percentage of women who may lose or gain access to resources (water, food, healthcare) is quantified.
[Response was provided in the Investment Feasibility Study]
The percentage of women who will gain new educational/professional opportunities is quantified
[Response was provided in the Investment Feasibility Study]
All possible negative impacts of the project on women, men or other gender groups have been identified
[Response was provided in the Investment Feasibility Study]

Are there management and institutional mechanisms in place to ensure gender equality?

A policy/code of conduct on non-discrimination and gender equality has been developed
[Response was provided in the Investment Feasibility Study]
A gender specialist/advisor is included in the project management structure
[Response was provided in the Investment Feasibility Study]
Mandatory training for project staff on gender equality and inclusion is provided
[Response was provided in the Investment Feasibility Study]
Not provided for by the project
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
Agreement _in the form of an exchange of notes_ between the Government of Ukraine and the Government of… - Agreement dated 06.06.2015 - d447782-20150902.pdf
08.08.2025
12:21:26 UTC

Alternative technical solutions

Technical Solution 1

Reconstruction of wastewater treatment facilities and construction of a technological line for the treatment and disposal of sludge at the Bortnytsia aeration station

Technical Solution 2

Reconstruction of the Bortnytsia aeration station

Total costs33'360'027'905 UAH65'150'000'000 UAH
  • For preparation
  • 1'000'000 UAH150'000'000 UAH
  • For implementation
  • 30'359'027'905 UAH50'000'000'000 UAH
  • For operation
  • 2'000'000'000 UAH10'000'000'000 UAH
  • For closing
  • 1'000'000'000 UAH5'000'000'000 UAH
    Average annual costs200'000'000 UAH300'000'000 UAH
    Project duration, incl.78 months120 months
  • Deadline for developing a FFS
  • 6 months24 months
  • Implementation period
  • 72 months96 months
    Service life600 months240 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Угодою передбачено залучення Японського генпідрядника

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Маштаб проєкту потребує залучення великої кількості субпідрядників

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Investment Feasibility Study]

    Маштаб проєкту потребує залучення великої кількості субпідрядників

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Проводилися процедури закупівлі та аналіз ринку

    What procurement strategy was chosen for the project implementation, and what justifies its feasibility in the context of the market and project objectives?
    Умови закупівлі передбачені кредитною угодою

    [Response was provided in the Investment Feasibility Study]

    What approaches are planned to be used to ensure transparency, competition, and efficiency in the procurement process?
    Закупівля буде проводитись за процедурою JICA на умовах FIDIC

    [Response was provided in the Investment Feasibility Study]

    What types of procurement procedures are envisaged by the project (open tender, negotiated procedure, competitive dialogue, etc.)?
    Open competitive bidding

    [Response was provided in the Investment Feasibility Study]

    Закупівля буде проводитись за процедурою JICA на умовах FIDIC

    Other

    [Response was provided in the Investment Feasibility Study]

    Закупівля буде проводитись за процедурою JICA на умовах FIDIC

    Competitive dialogue

    [Response was provided in the Investment Feasibility Study]

    Закупівля буде проводитись за процедурою JICA на умовах FIDIC

    Direct negotiation procedures

    [Response was provided in the Investment Feasibility Study]

    Закупівля буде проводитись за процедурою JICA на умовах FIDIC

    Pre-market engagement
    прямі запити до компаній

    [Response was provided in the Investment Feasibility Study]

    Potential market participants
    Угодою передбачено залучення Японського генпідрядника

    [Response was provided in the Investment Feasibility Study]

    Market readiness assessment
    В умовах збройної агресії російської федерації, японські компанії не виявляють бажання в реалізації проєкту через значні ризики.

    [Response was provided in the Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget33'360'027'905 UAH65'150'000'000 UAH
    Capital costs33'360'027'905 UAH65'150'000'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation1'000'000 UAH150'000'000 UAH
    For implementation30'359'027'905 UAH50'000'000'000 UAH
    For operation2'000'000'000 UAH10'000'000'000 UAH
    For closing1'000'000'000 UAH5'000'000'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitВартість водовідведення у Києві за 1 кубічний метр
    Service Unit Cost14 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    No – analysis not performed

    [Response was provided in the Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds138'421'007 UAH0 UAH
    Expected Funds494'677'568 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Investment Feasibility Study]

    Economic feasibility study - technical expertise

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Yes, successfully implemented 1 or more similar projects

    [Response was provided in the Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    Economic feasibility study - technical expertise

    [Response was provided in the Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Investment Feasibility Study]

    Strategic justification - forming a justification for the problem and need

    [Response was provided in the Investment Feasibility Study]

    Management rationale - public consultation

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Investment Feasibility Study]

    Management rationale - project management

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - communication with stakeholders

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Investment Feasibility Study]

    Management justification - other

    [Response was provided in the Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - risk management

    [Response was provided in the Investment Feasibility Study]

    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - working with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Management justification - legal support

    [Response was provided in the Investment Feasibility Study]

    Is there an understanding of where to find relevant experts and consultants?
    Yes, negotiations are already underway.

    [Response was provided in the Investment Feasibility Study]

    Is the project management structure defined: working group, chair, project team?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Проєкт діючий, створено Дирекцію.

    What categories of experts and consultants have already been involved at the project preparation stage?
    Specialists in interaction with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Environmental experts

    [Response was provided in the Investment Feasibility Study]

    Others

    [Response was provided in the Investment Feasibility Study]

    Financial consultants/modelers

    [Response was provided in the Investment Feasibility Study]

    Legal consultants

    [Response was provided in the Investment Feasibility Study]

    Commercial experts

    [Response was provided in the Investment Feasibility Study]

    Economic analysts

    [Response was provided in the Investment Feasibility Study]

    Strategic consultants

    [Response was provided in the Investment Feasibility Study]

    Technical experts

    [Response was provided in the Investment Feasibility Study]

    Social/gender consultants

    [Response was provided in the Investment Feasibility Study]

    Management experts / project managers

    [Response was provided in the Investment Feasibility Study]

    Are there plans to involve experts and consultants for further implementation of the project?
    No

    [Response was provided in the Investment Feasibility Study]

    Risk assessment

    Technical riskDefinedUndefined

    Organizational events

    ResponseDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

    Yes
    [Response was provided in the Investment Feasibility Study]

    В рамках діючої угоди надаютьсся послуги технічної допомоги

    Does the project require preparation assistance from Project Preparation Programs (PPF)?

    Development of a full feasibility study;
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Development of design and estimate documentation (DED);
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Other
    [Response was provided in the Investment Feasibility Study]

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Other
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]
    Need for financing

    Does the project require additional funding for preparation?

    No
    [Response was provided in the Investment Feasibility Study]