Restoration of the Srednyodneprovsky Shipping Lock of the State Enterprise "UKRVODSHLYAKH" after the Russian missile attack


Sector
Municipal infrastructure and services
Stream
Restoration, modernization and protection of critical infrastructure facilities to ensure their resilience to threats and the continuity of vital services
Maturity level
50
Project Status
Preliminary Investment Feasibility Study
Entry into Portfolio
State level of SPP
Investment Feasibility Study
Implementation
Completion

General information

Description of the project

The project envisages the repair of the lock's navigation chamber, the building of the central lock control panel, auxiliary structures and mechanisms of the Sredniodniprovsk navigation lock to restore navigation and the full functioning of the lock.

The purpose of the project

Main Goal:

Rebuilding the damaged/destroyed

Secondary Goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

Problems and solutions resulting from project implementation

Socio-economic context

Indicator

Value

Capital expenditure per year

81600 thous. UAH

Number of employees of the institution/institution/organization

62 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Protective Structures for Infrastructure Facilities

Stream

Restoration, modernization and protection of critical infrastructure facilities to ensure their resilience to threats and the continuity of vital services

Strategic document

Ukraine Facility Plan

Task

Reform 7 Component I Investments to strengthen Ukraine's energy infrastructure

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Збір офіційної статистичної інформації ДП «УКРВОДШЛЯХ»
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
2618 units
Annual demand for services/infrastructure
2
3436 units
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Alternative technical solutions

Technical Solution 1

Restoration of the SE "Seredniodniprovsky Shipping Lock" SE "UKRVODSHLYAKH"

Technical Solution 2

Restoration of the operability of the Sredniodniprovs'kyi shipping lock with the construction of an underground control panel

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)81'600'000 UAH1'000'000'000 UAH
For preparation1'500'000 UAH5'000'000 UAH
For implementation80'100'000 UAH995'000'000 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Average annual costs40'800'000 UAH200'000'000 UAH
Project duration, incl.24 months60 months
Deadline for developing a FFS6 months12 months
Implementation period18 months48 months
Service life240 months600 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget81'600'002 UAH1'000'000'002 UAH
Project cost (preparation and implementation)81'600'000 UAH1'000'000'000 UAH
For preparation1'500'000 UAH5'000'000 UAH
For implementation80'100'000 UAH995'000'000 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service Unitсередньодніпровський судноплавний шлюз
Service Unit Cost81'600'000 UAH

Profitability of the project

Is the project expected to generate income?NoNo
Is the project self-sustaining?No

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
No, this is the first project of its kind.

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Technical riskDefinedUndefined
Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Is there ongoing cooperation or support within the framework of international technical assistance (ITA) or from other donor or government agencies?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project require preparation assistance from Project Preparation Programs (PPF)?

Development of a full feasibility study;
[Response was provided in the Preliminary Investment Feasibility Study]
Finalization of existing documentation for the preparation of a preliminary feasibility study
[Response was provided in the Preliminary Investment Feasibility Study]
Updating existing documentation regarding the preparation of the feasibility study
[Response was provided in the Preliminary Investment Feasibility Study]
Need for financing

Does the project require additional funding for preparation?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
15/08/2025SP-N-150825-FE433F72State SPPreliminary Investment Feasibility StudyInclude--
01/10/2025SPP-N-011025-C1DFDB88State SPPPreliminary Investment Feasibility StudyInclude-50