General information
Description of the project
The building of the Municipal Non-Profit Enterprise of the Kamianka City Council "CPMSD No. 3" is a healthcare institution providing primary and secondary medical care. The year of construction of the building - 1979. Non-residential building (letter A-7) - seven-story (Block B) and three-story (Blocks A and B), with a technical floor and basement over the entire area of the building. Block A is adjacent to a one-story part (block A1) with a basement. The building is conditionally divided into blocks: Block A (in axes 1-7) - 91.6m x 12.6m; Block B (in axes 7-9) 12.7m x 55.2m; Block B (in axes 9 - 12) 32.8 x 16.2.
The implementation of the thermal modernization project has significant social and environmental benefits. As a result of the project implementation, the following will be achieved:
- Energy efficiency and emission reduction: thermal modernization of buildings allows to significantly reduce energy consumption and reduce emissions of harmful substances into the atmosphere. This contributes to improving air quality, reducing the impact on climate change and public health.
- Economic benefits: the implementation of thermal modernization can lead to significant economic benefits. Reducing the cost of heating and cooling buildings helps to reduce energy bills.
- Ensuring comfortable conditions for patients and medical staff in the institution and improving the quality of medical services.
The purpose of the project
Main Goal:
Introducing innovations and energy-efficient solutions
Secondary Goal:
Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
28066 human
Number of jobs, including for IDPs
206 human
Capacity
295698 human
Population in the geographical area of influence of the project
428605 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Improving energy efficiency in public buildings
Strategic document
Стратегія розвитку територіальної громади
Task
2.3.4. Improving energy efficiency and energy conservation
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Have the greenhouse gas emissions or emission reductions (Scope 1-2) associated with the project been calculated for a typical year and the entire project period?
Does the project require an environmental impact assessment (EIA) in accordance with the Law of Ukraine "On Environmental Impact Assessment"?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Were consultations held with representatives of target groups to take into account gender equality issues in the project?
Have the gender risks and social impacts of the project been assessed?
Are there management and institutional mechanisms in place to ensure gender equality?
Alternative technical solutions
Technical Solution 1
Reconstruction of the building (letter A-7) of the KNP KMR "CPMSD No. 3" at the address: Dnipropetrovsk region, Kamianske, Budivelnykiv Boulevard, 23
Technical Solution 2
Current renovation of a healthcare facility department
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]
[Response was provided in the Investment Feasibility Study]