Creation of an educational space within the framework of the "New Ukrainian School" reform of the Kamyansk territorial community of the Dnipropetrovsk region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Creation of a modern educational space: one natural science classroom (chemistry classroom) in the Lyceum "1", one natural science classroom (biology classroom) in the Gymnasium No. 4, one natural science classroom (physics classroom) in the Gymnasium No. 7, one natural science classroom (physics classroom) in the Gymnasium No. 9, one natural science classroom (physics classroom) in the Academy Lyceum No. 15, one natural science classroom (biology classroom) in the Gymnasium No. 18, one natural science classroom (chemistry classroom) in the Gymnasium No. 28, one natural science classroom (chemistry classroom) in the Gymnasium No. 34, one natural science classroom natural sciences (biology room) in the Lyceum No. 37. Creation of an educational space in the pilot lyceum Lyceum No. 39, namely: three classrooms in the natural sciences, one classroom in the mathematical field, two natural sciences laboratories, one STEM laboratory and one robotics technology field. And a separate area in the Lyceum No. 20 will be the "Defense of Ukraine" center, within which one classroom, one pre-medical training room (simulation class), one pneumatic shooting range, one tactical training and UAV control room will be equipped. To create a modern educational space, current repairs will be carried out and the necessary equipment will be purchased.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Improving the condition of infrastructure
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
4022 human
Number of employees of the institution/institution/organization
701 human
Number of IDP users
496 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Providing secondary education institutions with teaching aids and equipment within the framework of the implementation of the "New Ukrainian School" reform
Strategic document
Стратегія розвитку територіальної громади
Task
3.2.1. Affordable quality education
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Creating an educational space within the framework of the "New Ukrainian School" reform
Technical Solution 2
Modernization of educational space in selected educational institutions, but without complying with the requirements established by the Ministry of Education and Science of Ukraine as part of the "New Ukrainian School" reform.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]