Unhindered access to quality education - school buses. Bus for the Zinkivka Support Lyceum named after M.K.Zerov of the Zinkivka City Council


Sector
Education and science
Stream
Unhindered access to quality education - school buses
Maturity level
81
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

This direction is important for ensuring equal access to education, especially for students in rural areas and remote areas. Organized transportation promotes regular attendance, reduces educational inequality, and creates safe conditions for children to participate in the educational process. The purchase of school buses is carried out to ensure transportation of secondary school students and teaching staff to educational institutions 

The purpose of the project

Main Goal:

Improving the equality of wealth distribution

Secondary Goal:

Increasing compliance with modern standards, Ensuring inclusiveness and equal opportunities

Description of the purpose of the project and ways to achieve it

In connection with the planned optimization of the network of lyceum branches at the beginning of the 2026-2027 academic year, namely the liquidation of the branch of the "Bobrivnytsia Gymnasium" and the branch of the "Shengariivska Gymnasium", there is a need to transfer the educational process of students of these institutions to the base institution in the city of Zinkiv.

Problems and solutions resulting from project implementation

In connection with the reorganization of institutions, problems arise: 1. Increase in the contingent: The estimated number of students from the villages of Bobrivnyk and Shengarievka who will need daily transportation is 80 people. 2. Capacity deficit: The existing fleet of school buses of the lyceum is currently 100% loaded. Current logistics do not allow integrating new routes without significant disruption of traffic schedules and exceeding passenger capacity standards. 3. Social risks: The lack of guaranteed and comfortable transportation may cause justified concern among the parent community and hinder the adaptation of children to studying in a support institution. Taking into account the above and in order to ensure equal access to quality education, there is a need to purchase 1 additional unit of a specialized school bus.

Socio-economic context

Indicator

Value

Number of people who will use the service

80 human

Other functional

1 units

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Unhindered access to quality education - school buses

Strategic document

Стратегія розвитку територіальної громади

Task

1.1.2 1.1.2. Providing transportation for children and teachers to the place of study.

Project objectives

Indicator
Base value
Target value
Number of buses purchased (including for transporting children with disabilities)
0 units
1 units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Метод кінцевого використання
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
85 human
Annual demand for services/infrastructure
2
90 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Calculation of the cost of the bus.docx
09.03.2026
10:50:24 UTC

Alternative technical solutions

Technical Solution 1

Unhindered access to quality education - school buses. Bus for the Zinkivka Support Lyceum named after M.K.Zerov of the Zinkivka City Council

Technical Solution 2

Procurement of transportation services for students and teachers

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)3'576'000 UAH796'250 UAH
For implementation3'576'000 UAH796'250 UAH
Project operation and closure cost0 UAH0 UAH
Average annual costs357'600 UAH0 UAH
Project duration, incl.8 months13 months
Deadline for developing a FFS1 month1 month
Implementation period7 months12 months
Service life120 months12 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget3'576'000 UAH796'250 UAH
Project cost (preparation and implementation)3'576'000 UAH796'250 UAH
For preparation0 UAH0 UAH
For implementation3'576'000 UAH796'250 UAH
Project operation and closure cost0 UAH0 UAH
For operation0 UAH0 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitСередня вартість проєкту на одного отримувача послуги
Service Unit Cost44'700 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
10/03/2026SP-L-100326-82A93751Community SPInvestment Feasibility StudyInclude--
16/03/2026SP-N-160326-57297CCFState SPInvestment Feasibility StudyInclude--
11/03/2026SPP-L-110326-E1CA5977Community SPPInvestment Feasibility StudyInclude-81