Reconstruction of the power supply system of the Tyachiv MKZ "SPORTS ARENA" building at the address Tyachiv, Vajdy St., 15 by installing a rooftop solar power plant with a capacity of 119.5 kW
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The project involves the modernization of the power supply of the MKZ "Sportivna Arena" building in Tyachiv by installing a rooftop solar power plant with a capacity of 119.5 kW to cover the institution's own needs. The work includes the installation of photovoltaic panels on the roof, inverter equipment, electrical panels and protective automation, laying cable lines, installing grounding and surge protection systems with connection to the facility's internal networks. The expected result is a sustainable and economical power supply for the sports arena, reducing electricity costs, increasing the energy independence and reliability of the facility's operation, as well as reducing CO₂ emissions by replacing part of the electricity consumption with "green" generation. The estimated annual output of the solar power plant will be about 140.7 thousand kWh.
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Creation of new facilities and services, Поява нових виробничих потужностей
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of people who will use the service
2145 human
Strategic Case
Strategic feasibility of the project
Sector
Energy Sector
Subsector
Renewable energy and alternative fuels
Stream
Construction of new generating capacities
Strategic document
Стратегія розвитку територіальної громади
Task
3.3.3 https://tyachiv-city.gov.ua/strategiya-integrovanogo-rozvitku-gromadi-08-09-21-06-06-2017/
Project objectives
Project Sustainable Development Goals
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Reconstruction of the power supply system of the Tyachiv MKZ "SPORTS ARENA" building at the address Tyachiv, Vajdy St., 15 by installing a rooftop solar power plant with a capacity of 119.5 kW
Technical Solution 2
"Construction of solar carports on the territory of the MKZ "Sportivna Arena Tyachiv" with connection to internal networks (approximately 120 kW)"
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Is the project expected to generate income?
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]