Major renovation of the second building of the Children's School of Arts with the arrangement of a barrier-free environment for accessibility for low-mobility groups at the address: Kyiv region, Vyshgorod district, Slavutych city, Nezalezhnosti avenue, 9


Sector
Municipal infrastructure and services
Stream
Creating barrier-free routes and implementing barrier-free solutions
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

Creating a modern, inclusive educational and cultural space, accessible to all categories of visitors, including children and adults with disabilities, by completely modernizing the entrance group and the adjacent territory in accordance with the norms of DBN V.2.2-40:2018. The implementation of the project will ensure equal access to art education for children with special needs and will allow the school to become a full-fledged center of cultural life of the community, open to every resident of Slavutych.

The purpose of the project

Main goal:

Ensuring inclusiveness and equal opportunities

Secondary goal:

Improving the equality of wealth distribution, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

Ensuring the constitutional right to equal access to art education and cultural development for all children and adults, regardless of their physical abilities. The project involves the full adaptation of the entrance group, the adjacent territory and the interior of the second building of the school to the needs of low-mobility population groups (MGN) in accordance with DBN V.2.2-40:2018 “Inclusivity of buildings and structures”. Social inclusion: Creating conditions under which children with disabilities will be able to visit the institution independently or with minimal accompaniment, which will contribute to their socialization and creative realization. Visitor safety: Minimizing the risk of injury to students, teachers and visitors (including the elderly and parents with wheelchairs) by eliminating slippery surfaces, installing handrails and proper lighting. Infrastructure modernization: Updating outdated architectural elements of the Soviet period, bringing the aesthetics of the entrance group to modern standards of the urban environment of Slavutych.

Problems and solutions resulting from project implementation

The project includes: installation of tactile internal and external navigation; installation of a lift on the porch and a lift in the hall on the first floor for access to the second floor of the building; installation of a universal toilet cabin for people with reduced mobility and installation of a 3-stall toilet for school students; installation of an entrance porch adapted for people with disabilities and people with reduced mobility; replacement of doors; installation of paving slabs; repair and finishing works.

Socio-economic context

Indicator

Value

Number of people who will use the service

20865 human

Number of users from low-mobility population groups

1228 human

Number of IDP users

1285 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Urban planning and landscaping

Stream

Creating barrier-free routes and implementing barrier-free solutions

Strategic document

Стратегія розвитку територіальної громади

Task

4 Implementation of modern urban planning and development practices, creation of barrier-free routes and inclusive infrastructure, within the framework of the project of the Ministry of Development of Communities, Territories and Infrastructure of Ukraine "Barrier-Free Movement"

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
36_KD_ZKR.xls
23.02.2026
08:49:30 UTC

Alternative technical solutions

Technical Solution 1

Major renovation of the second building of the Children's School of Arts with the arrangement of a barrier-free environment for accessibility for low-mobility groups at the address: Kyiv region, Vyshgorod district, Slavutych city, Nezalezhnosti avenue, 9

Technical Solution 2

Reconstruction of the second building of the Children's School of Arts with the arrangement of a barrier-free environment for accessibility for low-mobility groups at the address: Kyiv region, Vyshgorod district, Slavutych city, Nezalezhnosti avenue, 9

Total costs4'099'772 UAH7'880'001 UAH
  • For preparation
  • 460'000 UAH830'000 UAH
  • For implementation
  • 3'624'771 UAH7'000'000 UAH
  • For operation
  • 15'000 UAH50'000 UAH
  • For closing
  • 1 UAH1 UAH
    Average annual costs15'000 UAH50'000 UAH
    Project duration, incl.3 months11 months
  • Deadline for developing a FFS
  • 1 month5 months
  • Implementation period
  • 2 months6 months
    Service life180 months600 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget4'099'772 UAH7'880'001 UAH
    Capital costs4'099'772 UAH7'880'001 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation460'000 UAH830'000 UAH
    For implementation3'624'771 UAH7'000'000 UAH
    For operation15'000 UAH50'000 UAH
    For closing1 UAH1 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitВартість ремонтних робіт на 1 метр квадратний
    Service Unit Cost5'178 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds460'000 UAH0 UAH
    Expected Funds4'084'771 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    None of the options are applicable
    Does the team have experience implementing similar projects?
    Partially, we have limited experience

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    None of the options are applicable
    Is there an understanding of where to find relevant experts and consultants?
    Partially, we are considering options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Financial riskDefinedUndefined
    Economic riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    24/02/2026SP-L-240226-571DF450Community SPInvestment Feasibility StudyInclude-
    06/03/2026SPP-L-060326-4C5CA1EFCommunity SPPInvestment Feasibility StudyInclude-