Major renovation of the building "International Business Development Center "Slavutych XXI Century" (Administrative Services Center) with the arrangement of a barrier-free environment for accessibility for low-mobility groups at the address: Kyiv region, Vyshhorod district, Slavutych, 2 Heroiv Dnipra st.
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
Transformation of the main center for providing administrative services of the city into a space of full accessibility, where every resident, regardless of physical abilities, can freely and with dignity receive state services. Creation of a modern European service center that guarantees equal rights and comfort for 100% of visitors, including people with disabilities, the elderly and families with children. The project was developed taking into account the requirements of DBN V.2.2-40:2018 "Inclusivity of buildings and structures".
The purpose of the project
Main goal:
Ensuring inclusiveness and equal opportunities
Secondary goal:
Improving the equality of wealth distribution, Improving the condition of infrastructure, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of users from low-mobility population groups
1228 human
Number of IDP users
1285 human
Number of people who will use the service
20865 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
Urban planning and landscaping
Stream
Creating barrier-free routes and implementing barrier-free solutions
Strategic document
Стратегія розвитку територіальної громади
Task
4 Implementation of modern urban planning and development practices, creation of barrier-free routes and inclusive infrastructure, within the framework of the project of the Ministry of Development of Communities, Territories and Infrastructure of Ukraine "Barrier-Free Movement"
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major renovation of the building "International Business Development Center "Slavutych XXI Century" (Administrative Services Center) with the arrangement of a barrier-free environment for accessibility for low-mobility groups at the address: Kyiv region, Vyshhorod district, Slavutych, 2 Heroiv Dnipra st.
Technical Solution 2
Reconstruction of the building "International Business Development Center "Slavutych XXI Century" (Administrative Services Center) with the arrangement of a barrier-free environment for accessibility for low-mobility groups at the address: Kyiv region, Vyshhorod district, Slavutych, 2 Heroiv Dnipra st.
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]