Description of the project
Installation of fire protection in educational institutions is a critical requirement of Ukrainian legislation (DBN V.2.5-56:2014) for fire prevention, rapid fire detection, notification and safe evacuation of people. This is necessary due to the large number of children, the risk of panic, the presence of hazardous materials and the need for protection during the operation of shelters.
The purpose of the project
Main Goal:
Improving the condition of infrastructure
Secondary Goal:
Increasing compliance with modern standards, Increasing compliance with modern standards, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of employees of the institution/institution/organization
68 human
Number of people who will use the service
490 human
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Забезпечення протипожежним захистом закладу освіти
Strategic document
Стратегія розвитку територіальної громади
Task
2.3. Якісна та ефективна освіта в безпечному просторі.
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Installation of fire protection systems at the facility "Ozerna Lyceum, Ternopil district, Ternopil region", at the address: 1 Zarudka Street, Ozerna village, Ternopil region
Technical Solution 2
Modernization of the fire protection system to ensure a safe educational space
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]