Major repairs of the civil defense protective structure No. 13844 of the KNP "Kryvyi Rih ML No. 3" of the KMR at the address: 13K, Hirnich Inzhenirov St., Kryvyi Rih, Dnipropetrovsk region, with the preparation of design and estimate documentation
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
Creating safe and proper conditions for patients, medical staff and hospital visitors during the legal regime of martial law. Ensuring uninterrupted provision of medical care in emergency situations.Restoration of structures: Waterproofing of premises, repair of walls, floors and ceilings using specialized materials resistant to moisture and fungus.Modernization of engineering networks: Complete replacement of power supply, water supply and sewage systems.Installation of ventilation: Installation of a modern filter ventilation system to purify the air and maintain the necessary microclimate.Ensuring inclusion: Adaptation of the entrance and interior space for low-mobility groups of the population (ramps, wide doorways, handrails, special bathrooms).
The purpose of the project
Main goal:
Increasing compliance with modern standards
Secondary goal:
Ensuring inclusiveness and equal opportunities
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Number of IDP users
7783 human
Number of people who will use the service
180 human
Population in the geographical area of influence of the project
64394 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring safe conditions in healthcare facilities
Strategic document
Стратегія розвитку територіальної громади
Task
1.3.1 Improving the centralized alert system and increasing the stock of civil defense protective structures (in particular in educational, healthcare, cultural, and social protection institutions) taking into account the principles of inclusiveness and accessibility
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Major repairs of the civil defense protective structure No. 13844 of the KNP "Kryvyi Rih ML No. 3" of the KMR at the address: 13K, Hirnich Inzhenirov St., Kryvyi Rih, Dnipropetrovsk region, with the preparation of design and estimate documentation
Technical Solution 2
Construction of a new protective structure
[The technical approach was selected for further detailed analysis or implementation.]
[The project initiator has not taken any decision about this alternative technical approach.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]