Reclamation of solid household waste landfill


Sector
Municipal infrastructure and services
Stream
Development of a system for the collection, transportation, recovery and disposal of household waste
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SP
Implementation
Completion

General information

Description of the project

land restoration after the end of landfill operation

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The remediation of the first stage of the Zhovti Vody MSW landfill is to ensure environmental safety and environmental protection, as well as prevent emergencies caused by the landfill overcrowding. The project is aimed at eliminating potential negative environmental consequences, in particular: pollution of water resources, atmospheric air due to the release of harmful gases, as well as soil contamination with toxic substances, which can lead to a deterioration in the quality of life and health of the population

Problems and solutions resulting from project implementation

The first stage of the Zhovti Vody municipal solid waste landfill is completely full, which creates risks of soil contamination, the lack of biogas and leachate collection and disposal systems creates risks of air and groundwater pollution, as well as the threat of emergency situations. To solve these problems, it is planned to implement a project to rehabilitate the first stage of the landfill, which will improve the ecological condition of the territory, increase the level of safety and quality of life of the population, and create conditions for further safe and rational use of community lands

Socio-economic context

Indicator

Value

Population in the geographical area of influence of the project

6316 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Household waste management

Stream

Development of a system for the collection, transportation, recovery and disposal of household waste

Strategic document

Стратегія розвитку територіальної громади

Task

B3.1 Improving the collection and treatment of household waste

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
project photo.docx
05.11.2025
13:31:59 UTC

Alternative technical solutions

Technical Solution 1

recultivation of the first stage of the MSW landfill

Technical Solution 2

MSW landfill reclamation

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)28'300'000 UAH28'300'000 UAH
For preparation3'300'000 UAH3'300'000 UAH
For implementation25'000'000 UAH25'000'000 UAH
Project operation and closure cost2'100'000 UAH2'100'000 UAH
For operation2'100'000 UAH2'100'000 UAH
Average annual costs738 UAH0 UAH
Project duration, incl.24 months24 months
Deadline for developing a FFS12 months12 months
Implementation period12 months12 months
Service life360 months360 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Pending

[The project initiator has not taken any decision about this alternative technical approach.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget30'400'000 UAH30'400'000 UAH
Project cost (preparation and implementation)28'300'000 UAH28'300'000 UAH
For preparation3'300'000 UAH3'300'000 UAH
For implementation25'000'000 UAH25'000'000 UAH
Project operation and closure cost2'100'000 UAH2'100'000 UAH
For operation2'100'000 UAH2'100'000 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
No
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitрекультивація
Service Unit Cost738 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

Other
[Response was provided in the Investment Feasibility Study]
Updating existing documentation regarding the preparation of design and estimate documentation (DED)
[Response was provided in the Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
05/11/2025SP-L-051125-7043F1C1Community SPInvestment Feasibility StudyIncludeThis project is included in the priority area-