Reconstruction of the stadium (2 stands, football field, running tracks) at 23 Stolyarchuk St. in Khmilnyk, Vinnytsia region" Khmilnyk Children's and Youth School of Khmilnyk City Council, Vinnytsia region.


Sector
Education and science
Stream
Ensuring proper development of the sports industry
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project includes the reconstruction of the sports center (installation of a football field with a natural turf surface, athletics tracks, stands for spectators, installation of sports equipment and a drainage system for the football field)

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Improving the equality of wealth distribution, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

Creation of a modern, safe and energy-efficient sports infrastructure for training and competitions of children's and youth teams, increasing the level of physical culture of the community population. Methods of achieving the goal: Preparatory stage - inventory of facilities, analysis of technical condition, public discussion and approval of the reconstruction project. Financial and economic stage - financing the project Design and estimate stage - development of project documentation, obtaining permits and approvals, determining the contractor. Construction and installation stage - implementation of major repair and construction works according to the schedule. Final stage - improvement of the territory, quality control of works, commissioning of the stadium. Information and communication stage - holding the opening of the stadium, advertising campaign, involving the local community in its use.

Problems and solutions resulting from project implementation

Problem: The existing infrastructure does not meet the requirements of modern training and competition standards, which limits the development of children's and youth sports in the city. As a result of the project implementation, the following will occur: Increase in the number of children involved in sports by 30–40%; Possibility of holding city and regional competitions; Increasing the prestige of the sports school; Energy saving up to 40%; Creation of a comfortable space for the community.

Socio-economic context

Indicator

Value

Number of people who will use the service

2000 human

Number of IDP users

250 human

Number of users from low-mobility population groups

9 %

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

Extracurricular education

Stream

Ensuring proper development of the sports industry

Strategic document

Стратегія розвитку територіальної громади

Task

1 Development (reconstruction) of sports infrastructure

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Методологія оцінки попиту на реконструкцію стадіону: Соціально-демографічний аналіз. Вивчення кількості населення громади, зокрема: частки дітей, молоді та активного працездатного населення; кількості спортсменів, учнів спортивних шкіл; наявності маломобільних груп населення, для яких потрібно забезпечити доступність. Дані беруться зі статистичних звітів, даних управлінь освіти, молоді та спорту. Аналіз наявної інфраструктури. Визначення, які спортивні об’єкти вже існують у місті чи громаді. Порівняння технічного стану, пропускної здатності, функціональності. Виявлення “прогалин” — наприклад, відсутності легкоатлетичних доріжок, освітлення чи місць для інклюзивного спорту. Статистичний прогноз попиту Розрахунок очікуваної кількості користувачів стадіону після реконструкції . Оцінка сезонності використання (наприклад, більша активність навесні та восени). Економічний аналіз Визначення потенційних джерел доходу (оренда, проведення заходів). Вивчення подібних реконструкцій у сусідніх містах або громадах. Оцінка, як змінилася відвідуваність і попит після модернізації там.

Has data from external sources been used in the demand assessment?

Yes

Нормативно-правові акти, порівняльні приклади

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes

Програма економічного і соціального розвитку громади

Indicator
Year
Demand
Annual demand for services/infrastructure
25
300 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Investment Feasibility Study]

Використання матеріалів із вторинної сировини, переробка будівельних відходів, повторне використання існуючих конструкцій. Планується впровадження роздільного збору відходів під час експлуатації стадіону.

Climate change adaptation
[Response was provided in the Investment Feasibility Study]

Проєкт включає облаштування дренажної системи, водопроникного покриття, озеленення території, що знижує ризики підтоплень і перегріву. Заплановане використання місцевих стійких рослин сприятиме адаптації до кліматичних змін.

Pollution prevention and control
[Response was provided in the Investment Feasibility Study]

Усі будівельні процеси відбуватимуться з дотриманням санітарно-екологічних норм. Передбачено зниження пилових і шумових викидів, а також утилізацію відходів без шкоди довкіллю.

Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Встановлення систем збору дощової води для поливу зелених зон і покриттів стадіону. Передбачено локальні очисні споруди для відведення дощових стоків без забруднення навколишнього середовища.

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]

Проєкт включає озеленення території,

Climate change mitigation
[Response was provided in the Investment Feasibility Study]

Під час реконструкції передбачено використання енергоефективних технологій: світлодіодне освітлення, енергоощадні системи водопостачання, застосування екологічних будівельних матеріалів. Зменшується споживання енергії та викиди CO₂.

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

Protecting and restoring biodiversity and ecosystems
[Response was provided in the Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Investment Feasibility Study]
Transition to a circular economy
[Response was provided in the Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Investment Feasibility Study]

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

The project may result in the forced displacement of women, men and other gender groups or loss of access to resources
[Response was provided in the Investment Feasibility Study]
Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other gender risks
[Response was provided in the Investment Feasibility Study]
There are risks of impaired mobility or safety for women, men and other gender groups during construction/operation
[Response was provided in the Investment Feasibility Study]
There is a risk of reduced economic opportunities for women, men and other gender groups (e.g. loss of jobs or retail outlets)
[Response was provided in the Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Investment Feasibility Study]
Other benefits from project implementation
[Response was provided in the Investment Feasibility Study]
Envisaged training or advanced training for women in the private sector
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Investment Feasibility Study]

Documents

Name
Date
On approval of the Procedure and conditions for providing in 2021 sub-… - Resolution No. 226 of 03/17/2021 - d503856-20211007.pdf
06.11.2025
12:54:58 UTC

Alternative technical solutions

Technical Solution 1

Reconstruction of the stadium (2 stands, football field, running tracks) at 23 Stolyarchuk St. in Khmilnyk, Vinnytsia region, Khmilnyk Children's and Youth School of Khmilnyk City Council, Vinnytsia region.

Technical Solution 2

Major repairs of stands and arrangement of sports infrastructure

Total costs44'000'000 UAH44'000'000 UAH
  • For preparation
  • 200'000 UAH200'000 UAH
  • For implementation
  • 39'780'000 UAH39'780'000 UAH
  • For operation
  • 4'000'000 UAH4'000'000 UAH
  • For closing
  • 20'000 UAH20'000 UAH
    Average annual costs400'000 UAH200'000 UAH
    Project duration, incl.20 months20 months
  • Deadline for developing a FFS
  • 2 months2 months
  • Implementation period
  • 18 months18 months
    Service life120 months120 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    0
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Ринок будівельно-монтажних робіт в Україні, зокрема у сфері реконструкції спортивних споруд і стадіонів, є конкурентним та динамічним. На ньому діє значна кількість підрядних організацій різного рівня — від місцевих до національних, які мають досвід реалізації подібних об’єктів, сертифікованих спеціалістів та необхідну технічну базу.

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Investment Feasibility Study]

    Проєкт реконструкції стадіону становить значний інтерес для малих і середніх підприємств, оскільки передбачає широкий спектр робіт

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Investment Feasibility Study]

    Проєкт реконструкції стадіону передбачає використання сучасних технологій, матеріалів та обладнання, частина з яких може бути вироблена міжнародними компаніями. Водночас, значна частина будівельно-монтажних, інженерних і оздоблювальних робіт може бути виконана національними підрядниками — будівельними компаніями, постачальниками бетону, металоконструкцій, сантехнічних і електромонтажних систем.

    Has an analysis of available procurement options been conducted for the technical solution?
    No

    [Response was provided in the Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget44'000'000 UAH44'000'000 UAH
    Capital costs44'000'000 UAH44'000'000 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation200'000 UAH200'000 UAH
    For implementation39'780'000 UAH39'780'000 UAH
    For operation4'000'000 UAH4'000'000 UAH
    For closing20'000 UAH20'000 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    No
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitCередня вартість проєкту на одного отримувача послуги
    Service Unit Cost80'000 UAH

    Profitability of the project

    Is the project expected to generate income?

    ResponseNoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    The project does not fall under the PPP format by its nature/character

    [Response was provided in the Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Investment Feasibility Study]

    Economic feasibility study - technical expertise

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    No, this is the first project of its kind.

    [Response was provided in the Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    Economic feasibility study - technical expertise

    [Response was provided in the Investment Feasibility Study]

    потрібен ліцензований технічний експерт

    Economic justification - social and gender analysis

    [Response was provided in the Investment Feasibility Study]

    консультанта з соціальної політики залучити

    Strategic justification - forming a justification for the problem and need

    [Response was provided in the Investment Feasibility Study]

    Management rationale - public consultation

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Investment Feasibility Study]

    залучити експерта еколога

    Management rationale - project management

    [Response was provided in the Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - communication with stakeholders

    [Response was provided in the Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Investment Feasibility Study]

    потрібен консультант з публічних інвестицій

    Management justification - other

    [Response was provided in the Investment Feasibility Study]

    потрібен експерт з технічного нагляду

    Financial analysis - financial analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - risk management

    [Response was provided in the Investment Feasibility Study]

    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Investment Feasibility Study]

    доцільно залучити консультанта з регіонального розвтку/ стратегічного планування

    Strategic rationale - demand analysis

    [Response was provided in the Investment Feasibility Study]

    Management rationale - working with international financial organizations (IFOs)

    [Response was provided in the Investment Feasibility Study]

    Management justification - legal support

    [Response was provided in the Investment Feasibility Study]

    Is there an understanding of where to find relevant experts and consultants?
    Partially, we are considering options

    [Response was provided in the Investment Feasibility Study]

    Risk assessment

    Technical riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    Other
    [Response was provided in the Investment Feasibility Study]
    Finalization of existing documentation for the preparation of a preliminary feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of the feasibility study
    [Response was provided in the Investment Feasibility Study]
    Updating existing documentation regarding the preparation of design and estimate documentation (DED)
    [Response was provided in the Investment Feasibility Study]