Energy saving measures. Reconstruction of the boiler house at Mykola Khodych, 15, with the installation of a block-modular boiler house, Kryvyi Rih, Dnipropetrovsk region. Adjustments
- Preparation
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
General information
Description of the project
The block-modular boiler house (BMK) is designed to supply thermal energy for heating needs to existing consumers of the municipal enterprise of heat networks "Kryvorizhteplomerezha". The boiler plant equipment is mounted inside the container. The container structure is welded, made of steel sheets and profiles, with a 100 mm thick insulation made of non-combustible material. The degree of fire resistance of the container is IIIa according to DBN V.1.1-7. The communications exits are through the walls of the container. The boiler plant is made on the basis of two steel fire-tube water-heating gas boilers. Natural gas is used to produce thermal energy, which is supplied to the boiler house via a designed pipeline from the existing gas pipeline with a SHGRP installation to reduce the pressure to the design value. Structurally, the BMK provides for the possibility of switching to diesel fuel. The nominal thermal power of the boiler room equipment is 516 kW. The nominal thermal efficiency is 466 kW. The heat supply system is a closed two-pipe system. Thermal energy is released from the boiler room with heated water according to the temperature schedule T1-T2 = 90-70˚С. The maximum operating pressure is 0.6 MPa. The BMK-500 block-modular boiler room is a finished product (manufactured in accordance with TU U 28.2-20016760-026-2023), which is supplied by the manufacturer in a fully equipped form with all technological, construction and fire protection systems. This project does not develop the internal systems and equipment of the BMK. It is planned to connect the BMK to gas, heat, water, electricity and sewage networks.
The purpose of the project
Main goal:
Improving the equality of wealth distribution
Secondary goal:
Increasing compliance with modern standards, Increasing compliance with modern standards, Creation of new facilities and services, Increasing the even distribution of resources, Introducing innovations and energy-efficient solutions, Improving the quality of services, Meeting demand
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other economic
466 kW
Other economic
15 year
Other economic
0.48 MW
Number of people who will use the service
167 human
Strategic Case
Strategic feasibility of the project
Sector
Municipal infrastructure and services
Subsector
District Heating
Stream
Restoration, modernization and development of centralized and decentralized heating systems
Strategic document
Стратегія розвитку територіальної громади
Task
2.5.2 Reducing energy losses/consumption
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Documents
Alternative technical solutions
Technical Solution 1
Energy saving measures. Reconstruction of the boiler house at Mykola Khodych, 15, with the installation of a block-modular boiler house, Kryvyi Rih, Dnipropetrovsk region. Adjustments
Technical Solution 2
Reconstruction and modernization of the existing boiler house of Mykola Khodych, 15 Kryvyi Rih, Dnipropetrovsk region
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Preliminary cost breakdown
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]