Major repairs of the catering unit in Kryvyi Rih Gymnasium 93 of the Kryvyi Rih City Council. at the address: Kryvyi Rih, Dnipropetrovsk region, 11 John McCain St., 50053.


Sector
Education and science
Stream
Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

A combination of measures to ensure healthy nutrition: planning of premises and location of technological equipment, replacement of sewage systems, water supply, heating, ventilation, electric lighting and power networks, installation of grounding, installation of the SPZ system.

The purpose of the project

Main goal:

Increasing compliance with modern standards

Secondary goal:

Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

To provide a major overhaul of the school's catering unit to create safe and modern conditions for organizing student meals. The project is aimed at updating the premises and equipment in accordance with sanitary and safety standards, which will guarantee high-quality and healthy nutrition for children.

Problems and solutions resulting from project implementation

The school's dining hall, built in 1961, has dilapidated premises, engineering networks and equipment that do not meet sanitary and fire standards, which is why there are no proper conditions for high-quality and safe nutrition for students. As a result of the project, a modern dining hall equipped in accordance with state standards will be created, which will ensure daily safe and healthy nutrition for more than 469 students, including children with special educational needs, and will contribute to strengthening their health and improving the quality of the educational environment.

Socio-economic context

Indicator

Value

Number of people who will use the service

479 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Ensuring access to high-quality and safe food in educational institutions through the development of modern canteen infrastructure (food blocks)

Strategic document

Стратегія розвитку територіальної громади

Task

1.1.1. Ensuring equal access and improving the quality of preschool, general secondary education

Project objectives

Indicator
Base value
Target value
Number of children who received access to high-quality hot meals in modernized canteens (dining blocks)
0 human
479 human

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Оцінка проведена на основі демографічного аналізу (кількість учнів та прогноз контингенту), технічного аудиту стану харчоблоку та обладнання, перевірки відповідності санітарним і безпековим нормам, а також з урахуванням звернень батьківської та педагогічної громадськості.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
479 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Other benefits from project implementation
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to education (primary, secondary, vocational)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will create jobs available to women (temporarily or permanently)
[Response was provided in the Preliminary Investment Feasibility Study]
The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
financial analysis of the project CG No. 93 clarified.docx
11.02.2026
06:24:32 UTC

Alternative technical solutions

Technical Solution 1

Major renovation of the catering unit in Kryvyi Rih Gymnasium No. 93 of the Kryvyi Rih City Council

Technical Solution 2

Current renovation of the catering unit in Kryvyi Rih Gymnasium No. 93 of the Kryvyi Rih City Council

Total costs43'141'636 UAH6'134'905 UAH
  • For preparation
  • 406'700 UAH606'270 UAH
  • For implementation
  • 11'718'701 UAH5'225'500 UAH
  • For operation
  • 31'016'235 UAH303'135 UAH
    Average annual costs1'550'812 UAH12'657 UAH
    Project duration, incl.18 months12 months
  • Deadline for developing a FFS
  • 6 months6 months
  • Implementation period
  • 12 months6 months
    Service life240 months60 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, both national and international

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget43'141'636 UAH6'134'905 UAH
    Capital costs43'141'636 UAH6'134'905 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation406'700 UAH606'270 UAH
    For implementation11'718'701 UAH5'225'500 UAH
    For operation31'016'235 UAH303'135 UAH
    For closing0 UAH0 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service Unitодна
    Service Unit Cost25'314 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds406'700 UAH0 UAH
    Expected Funds406'700 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    No, this is the first project of its kind.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    None of the options are applicable
    Is there an understanding of where to find relevant experts and consultants?
    Partially, we are considering options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Technical riskDefinedUndefined
    Financial riskDefinedUndefined
    Economic riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    06/02/2026SP-L-060226-FAF457C8Community SPInvestment Feasibility StudyCancellation of the decision to include in a joint venture-
    11/02/2026SP-L-110226-610CD0E7Community SPInvestment Feasibility StudyInclude-
    18/02/2026SP-N-180226-DA858688State SPInvestment Feasibility StudyInclude-
    17/02/2026SPP-L-170226-AD66442FCommunity SPPInvestment Feasibility StudyInclude-