Arrangement of a barrier-free route connecting "Administrative Services Center - Smilyansk City Hospital on Sofiivska Street"


Sector
Municipal infrastructure and services
Stream
Створення безбар'єрних маршрутів громади
Maturity level
88
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves the construction of a barrier-free pedestrian route in the city of Smila, which will connect the premises of the administrative services center and the building of the municipal non-profit enterprise "Smilyanska City Hospital" on Sofiivska Street, through major repairs of sidewalks with the installation of accessibility elements, in particular, lowering the curbstone, laying tactile tiles, arranging pedestrian crossings and removing physical obstacles for low-mobility groups. 

The purpose of the project

Main Goal:

Ensuring inclusiveness and equal opportunities

Secondary Goal:

Increasing compliance with modern standards, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The project proposes to create conditions for unhindered movement of pedestrians, including people with disabilities, by carrying out major repairs of the sidewalk within the barrier-free route in the city of Smila, Cherkasy region.

Problems and solutions resulting from project implementation

The existing pedestrian infrastructure on the designated route has physical barriers (damaged sidewalks, lack of lowered curbs, tactile elements, and safe crossings), which complicates access for low-mobility groups to social infrastructure facilities and increases the risk of injuries, while the implementation of the project through major repairs of sidewalks and the installation of barrier-free elements will ensure safe, convenient, and equally accessible transportation for all community residents.

Socio-economic context

Indicator

Value

Population in the geographical area of influence of the project

55585 human

Number of IDPs in the geographical area of impact of the project

6814 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Development and Reconstruction of Subnational Infrastructure

Stream

Створення безбар'єрних маршрутів громади

Strategic document

Стратегія розвитку територіальної громади

Task

2.3.2 Розвинути транспортну та пішохідну інфраструктуру з урахуванням принципів доступності та сталої мобільності

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Застосовано описову методологію, що передбачала візуальне обстеження тротуару, аналіз інтенсивності пішохідного руху та звернень мешканців для підтвердження наявного попиту
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
25206 human
Annual demand for services/infrastructure
2
25300 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Transition to a circular economy
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
ENPV bar-free.pdf
11.03.2026
13:09:18 UTC

Alternative technical solutions

Technical Solution 1

Major repairs of sidewalks on the barrier-free route

Technical Solution 2

Current sidewalk repairs on the barrier-free route

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)35'340'000 UAH850'000 UAH
For preparation340'000 UAH50'000 UAH
For implementation35'000'000 UAH800'000 UAH
Project operation and closure cost0 UAH0 UAH
Average annual costs7'068'000 UAH0 UAH
Project duration, incl.8 months6 months
Deadline for developing a FFS2 months2 months
Implementation period6 months4 months
Service life60 months12 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
2
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget35'340'000 UAH850'000 UAH
Project cost (preparation and implementation)35'340'000 UAH850'000 UAH
For preparation340'000 UAH50'000 UAH
For implementation35'000'000 UAH800'000 UAH
Project operation and closure cost0 UAH0 UAH
For operation0 UAH0 UAH
For closing0 UAH0 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitСередня вартість проєкту на одного мешканця, який користуватиметься цим маршрутом
Service Unit Cost1'298 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds344'992 UAH0 UAH
Expected Funds344'992 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Yes, successfully implemented 1 or more similar projects

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Management rationale - working with international financial organizations (IFOs)

[Response was provided in the Preliminary Investment Feasibility Study]

Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Technical riskDefinedUndefined
Market riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

Finalization of existing documentation for the preparation of a preliminary feasibility study
[Response was provided in the Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
11/03/2026SP-L-110326-7CA9B2F7Community SPInvestment Feasibility StudyInclude--
19/03/2026SP-N-190326-C5F3F186State SPInvestment Feasibility StudyAwaiting review--
13/03/2026SPP-L-130326-65BE646ACommunity SPPInvestment Feasibility StudyIncludeapproved by the local investment council (minutes No. 2 dated 03/13/2026)88