Creation of a car service to meet the critical needs of the municipal non-profit enterprise "City Hospital No. 2" of the Kramatorsk City Council (purchase of vehicles).
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
Creation of a car service to ensure the uninterrupted operation of the catering unit of the municipal non-profit enterprise "City Hospital No. 2" of the Kramatorsk City Council. Purchase of PEUGEOT Partner Van or similar vehicles to meet the economic needs of a critically important medical enterprise in the city of Kramatorsk, namely vehicles for transporting food between hospital locations.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure, Creation of new jobs through project implementation, Improving the quality of services
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Capacity
1000 human
Capacity
1000 human
Number of employees of the institution/institution/organization
700 human
Number of users from low-mobility population groups
100 human
Number of IDP users
134 human
Number of people who will use the service
50000 human
Strategic Case
Strategic feasibility of the project
Sector
Healthcare
Subsector
Specialized medical care
Stream
Ensuring access to high-quality medical development and modernization of medical infrastructure facilities
Strategic document
Регіональна стратегія розвитку
Task
1.2.2. 1.2.2. Restoration of the tertiary (highly specialized) level of medical service provision
Project objectives
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Creation of a car service to provide inpatients with meals.
Technical Solution 2
Use of rented vehicles
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Team competencies
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]