Construction of sewerage on Naddnistryanska, Malekhivska, Konovaltsa, Mykolaivska, Kryvonosa streets, Pryam street, Prydorozhny lane, Novyi Rozdil town, Stryi district, Lviv region


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves the construction of a sewage network along Naddnistryanska, Malekhivska, Konovaltsa, Mykolaivska, Kryvonosa, Pryamya and Prydorozhnyi avenues in the town of Novy Rozdil, Stryi district, Lviv region. The work will include laying new sewer collectors, arranging connections for households, installing inspection wells, as well as conducting commissioning works. What problems does the project solve? Lack of a centralized sewage network on the specified streets. Use of cesspools and septic tanks, which creates a threat of groundwater contamination and worsening of the sanitary and epidemiological situation. Low level of comfort for residents and limited possibilities for connecting new residential and commercial buildings. Expected results Providing residents with a modern centralized sewage system. Reducing the environmental load and improving the state of the environment. Increasing the level of sanitary safety and quality of life of the population. Creating conditions for the further development of the city's residential and social infrastructure.

The purpose of the project

Main goal:

Improving the quality of services

Secondary goal:

Increasing compliance with modern standards, Improving the equality of wealth distribution, Improving the condition of infrastructure

Description of the purpose of the project and ways to achieve it

The purpose of the public investment project Providing residents of Naddnistryanska, Malekhivska, Konovaletsa, Mykolaivska, Kryvonosa, Pryam and Prydorozhnyi avenues in the city of Novy Rozdil with a modern centralized sewage system in order to increase the level of sanitary safety, improve the environmental situation and create conditions for the sustainable development of the city's housing and social infrastructure. Methods of achieving the goal construction of new sewer networks on designated streets; arrangement of inspection wells, connections for households and social infrastructure facilities; carrying out commissioning work and putting the system into operation; integration of networks into the general city sewage system. Justification of the gap between the current state and the planned result Today, residents of the specified streets do not have access to centralized sewage and are forced to use cesspools and local systems, which leads to: pollution of groundwater and deterioration of the environment; increased sanitary risks; limited opportunities for development of the territory and attraction of investments. The implementation of the project will allow to overcome this gap by creating an effective engineering infrastructure that meets modern requirements and will ensure an improvement in the quality of life of the population.

Problems and solutions resulting from project implementation

Key problems to be solved by the project Lack of a centralized sewage system on certain streets, which forces residents to use cesspools and local septic tanks. Deterioration of the sanitary and epidemiological situation, as the existing individual systems are not airtight and pose a threat to public health. Pollution of soils and groundwater used for household needs. Restrictions on the development of the territory, as the lack of engineering infrastructure complicates the connection of new residential and social facilities. Current relevance of the problems The number of residents and the load on the territory are growing, which increases environmental and sanitary risks. In the context of decentralization and increasing the role of communities in ensuring the quality of life, the lack of proper infrastructure is a serious obstacle to sustainable development. Compliance with European standards in the field of ecology and safety requires a transition from local to centralized systems. Possible consequences if the problem is not resolved Further deterioration of the environment, increased risk of drinking water pollution. Increased morbidity among the population. Decrease in the investment attractiveness of the territory and inhibition of the socio-economic development of the community. Expected positive changes from the implementation of the project Providing residents with a modern centralized sewage network. Improving sanitary and hygienic conditions and reducing environmental risks. Creating comfortable living conditions and developing new residential and social developments. Increasing the investment attractiveness of the community and improving the quality of life of the population.

Socio-economic context

Indicator

Value

Number of people who will use the service

588 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Restoration, development and modernization of centralized water supply and wastewater infrastructure

Strategic document

Стратегія розвитку територіальної громади

Task

2.4.1. Establish a water supply and drainage network.

Project objectives

Indicator
Base value
Target value
Share of population connected to centralized sewage network
0 %
100 %

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

розрахунок кількості домогосподарств та населення, що проживають на визначених вулицях (базується на даних місцевої ради та реєстру абонентів); прогноз демографічного розвитку території на основі офіційних статистичних даних; аналіз існуючих звернень мешканців до органів місцевого самоврядування з проханням забезпечити підключення до централізованої каналізації.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
34000 m3
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Sustainable use and protection of water and marine resources
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]
Climate change mitigation
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

The project will improve women's access to safe water, food, and medical services
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
economic feasibility study sewerage.pdf
23.10.2025
08:13:54 UTC

Alternative technical solutions

Technical Solution 1

Construction of sewerage on Naddnistryanska, Malekhivska, Konovaltsa, Mykolaivska, Kryvonosa streets, Pryam street, Prydorozhny lane, Novyi Rozdil town, Stryi district, Lviv region.

Technical Solution 2

Individual drainage systems for each household

Total costs49'579'062 UAH11'330'002 UAH
  • For preparation
  • 1'722'380 UAH330'000 UAH
  • For implementation
  • 47'706'681 UAH11'000'000 UAH
  • For operation
  • 150'000 UAH1 UAH
  • For closing
  • 1 UAH1 UAH
    Average annual costs150'000 UAH1'500'000 UAH
    Project duration, incl.26 months66 months
  • Deadline for developing a FFS
  • 2 months6 months
  • Implementation period
  • 24 months60 months
    Service life360 months120 months
    Target indicatorsDefined Defined
    Technical Solution Status
    Active

    [The technical approach was selected for further detailed analysis or implementation.]

    Rejected

    [The technical approach was not selected for further detailed analysis or implementation.]

    Components of a technical solution
    To components
    1
    To components
    0

    Commercial Justification

    Supplier and contractor market assessment

    Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is the project of interest to small and medium-sized enterprises?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Will the project involve national or international suppliers and contractors?
    Yes, only national

    [Response was provided in the Preliminary Investment Feasibility Study]

    Has an analysis of available procurement options been conducted for the technical solution?
    Yes

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial justification

    Total project budget

    Total preliminary budget49'579'062 UAH11'330'002 UAH
    Capital costs49'579'062 UAH11'330'002 UAH
    Operational costs0 UAH0 UAH

    Preliminary cost breakdown

    Operating costs for implementation0 UAH0 UAH
    For preparation1'722'380 UAH330'000 UAH
    For implementation47'706'681 UAH11'000'000 UAH
    For operation150'000 UAH1 UAH
    For closing1 UAH1 UAH
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Preliminary Investment Feasibility Study]
    Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
    Yes
    [Response was provided in the Investment Feasibility Study]

    Average project cost per service recipient

    Service UnitСередня вартість проєкту на одного отримувача (домогосподарство)
    Service Unit Cost84'063 UAH

    Profitability of the project

    Is the project expected to generate income?NoNo

    Availability of services

    Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
    Yes – the analysis was conducted, it was found that the tariffs correspond to the financial capabilities of consumers

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project Financing Mechanisms

    Are funding sources and mechanisms identified?

    Source and MechanismYesNo

    Funding Sources

    Approved Funds0 UAH0 UAH
    Expected Funds0 UAH0 UAH

    Public-private partnership

    Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
    No, no assessment was conducted.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
    No

    [Response was provided in the Preliminary Investment Feasibility Study]

    Management Rationale

    Team competencies

    Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
    Strategic justification - analysis of the strategic feasibility of the project

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - economic analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - communication with stakeholders

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - risk management

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - social and gender analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - public consultations

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of available procurement options

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - legal support

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - SDG compliance analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Project management - working with international financial organizations (IFOs)

    [Response was provided in the Preliminary Investment Feasibility Study]

    Financial analysis - financial analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Strategic rationale - demand analysis

    [Response was provided in the Preliminary Investment Feasibility Study]

    Economic justification - environmental expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Business case - analysis of the market environment

    [Response was provided in the Preliminary Investment Feasibility Study]

    Does the team have experience implementing similar projects?
    Yes, successfully implemented 1 or more similar projects

    [Response was provided in the Preliminary Investment Feasibility Study]

    Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
    Economic feasibility study - technical expertise

    [Response was provided in the Preliminary Investment Feasibility Study]

    Is there an understanding of where to find relevant experts and consultants?
    Yes, negotiations are already underway.

    [Response was provided in the Preliminary Investment Feasibility Study]

    Risk assessment

    Financial riskDefinedUndefined
    Results of the feasibility analysis
    Project Preparation Program Engagement and Funding Needs

    Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

    None of the options are applicable

    Project Approval History

    DateDecision NumberPortfolioProject StatusDecisionReasons
    17/10/2025SP-L-171025-9C39F9EBCommunity SPInvestment Feasibility StudyNot approved-
    23/10/2025SP-L-231025-A8ADB7DFCommunity SPInvestment Feasibility StudyNot approved-