Creation of an educational space within the framework of the "New Ukrainian School" reform - Fontansk rural territorial community of Odessa district, Odessa region
- General information
- Strategic Case
- Economic Case
- Commercial Case
- Financial Case
- Management Case
- Summary
General information
Description of the project
As part of the project, a modern physics classroom will be created in accordance with the standards of the New Ukrainian School at the LYCEUM "OLEKSANDRIVSKY" of the Fontansky Village Council of the Odessa District of the Odessa Region. Currently, the institution has the status of a "Lyceum", but in 2027 it is planned to change its status to a "gymnasium". It is planned to purchase educational and laboratory equipment for conducting demonstration and practical experiments in the main sections of physics. The classroom will be equipped with sets of laboratory instruments and measuring instruments for students to perform practical and laboratory work, demonstration sets for the teacher, models of physical processes and educational and visual materials, multimedia equipment. Also, the local budget provides for the repair of the classroom and utility room, and the purchase of furniture.
The purpose of the project
Main Goal:
Increasing compliance with modern standards
Secondary Goal:
Increasing compliance with modern standards
Description of the purpose of the project and ways to achieve it
Problems and solutions resulting from project implementation
Socio-economic context
Indicator
Value
Other economic
150 human
Other functional
1 units
Strategic Case
Strategic feasibility of the project
Sector
Education and science
Subsector
School education
Stream
Provision of general secondary education institutions with learning tools and equipment within the implementation of the “New Ukrainian School” reform
Strategic document
National Strategy for Building a Safe and Healthy Educational Environment in the New Ukrainian School
Task
IV Expected results of the implementation of the National Strategy
Project objectives
Project Sustainable Development Goals
Demand for the service and its dynamics
What methodology was used to estimate demand?
Has data from external sources been used in the demand assessment?
Does the demand forecast take into account the latest demographic and economic forecasts?
Analysis of the project's impact on ecology and climate change
Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?
Is the proposed project expected to significantly harm any of the following climate or environmental objectives?
Project sustainability and inclusivity
Identify potential gender risks of the project and indicate possible ways to overcome them:
Does the project provide for improving women's access to services?
Are civil society organizations representing women and vulnerable groups included in the consultation process?
Alternative technical solutions
Technical Solution 1
Creation of a modern physics classroom in accordance with the standards of the New Ukrainian School
Technical Solution 2
Phased modernization of the office with partial updating of the material and technical base
[The technical approach was selected for further detailed analysis or implementation.]
[The technical approach was not selected for further detailed analysis or implementation.]
Commercial Justification
Supplier and contractor market assessment
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]
Financial justification
Total project budget
Average project cost per service recipient
Profitability of the project
Availability of services
[Response was provided in the Preliminary Investment Feasibility Study]
Project Financing Mechanisms
Are funding sources and mechanisms identified?
Funding Sources
Public-private partnership
[Response was provided in the Preliminary Investment Feasibility Study]
[Response was provided in the Preliminary Investment Feasibility Study]