Major repairs of the fire alarm system in the premises of the Drohobych Scientific Lyceum named after Bohdan Lepky of the Drohobych City Council, Lviv region at the address: 19 B. Lepky St., Drohobych, Lviv region (Installation of a fire protection system)


Sector
Education and science
Stream
Arrangement of safe conditions in institutions providing general secondary education (fire protection)
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves major repairs of the fire alarm system in the premises of the Drohobych Scientific Lyceum named after Bohdan Lepky of the Drohobych City Council, Lviv region, located at: 19 B. Lepkogo St., Drohobych. The lyceum building is a facility with a large number of people - 780 students study here every day and 90 teachers work here, as well as 21 technical and service personnel. The fire alarm system, installed many years ago, is morally and technically outdated and does not meet modern fire safety requirements. The project involves installing a modern fire protection system, which includes: updating or replacing fire detectors, detectors, cable lines and control panels; integrating the system with a centralized fire monitoring station; carrying out commissioning work and checking the system's operability.

The purpose of the project

Main Goal:

Increasing compliance with modern standards

Secondary Goal:

Increasing compliance with modern standards, Improving the condition of infrastructure, Improving the quality of services

Description of the purpose of the project and ways to achieve it

The purpose of the project is to ensure an adequate level of fire safety in the Drohobych Scientific Lyceum named after B. Lepky of the Drohobych City Council of the Lviv region by modernizing the fire-fighting infrastructure. Main objectives: • creating safe conditions for students, teaching staff and visitors to the institution; • preventing the occurrence of fire-related emergencies; • bringing the facility into compliance with current fire safety regulations and state standards; • increasing the level of readiness of the institution to act in the event of a fire hazard. The implementation of the project will contribute to the preservation of the life and health of children and employees, as well as increase the overall safety of the educational process.

Problems and solutions resulting from project implementation

The building of the Drohobych Scientific Lyceum named after B. Lepky Lyceum has been in operation for a long time, while the existing fire alarm system is absent and does not meet modern fire safety requirements and state building codes. The lack of a modern automatic fire alarm system and a system for alerting and managing the evacuation of people creates a potential threat to the life and health of students, teaching staff and employees of the educational institution. Providing the educational institution with an appropriate fire alarm system will allow to protect the life and health of students, which will contribute to ensuring the implementation of the health-saving function of the final beneficiaries - children. The purpose of this project is: 1) obtaining high-quality modern education through free creative learning in accordance with social needs, determined by the development of the Ukrainian state; 2) creating conditions for each student to receive the level of education that corresponds to his abilities and individual characteristics; 3) creation of a viable system of education and upbringing of children to achieve their educational level in accordance with state standards 4) ensuring healthy conditions for development, self-enrichment, and personal improvement; 5) development of the intellectual and emotional sphere of the child. 6) development of health-preserving functions. As a result of the project, the educational infrastructure will be modernized, the quality of education will be improved by creating comfortable and safe conditions for staying in the lyceum. The implementation of the project will allow to increase the level of safety of participants in the educational process. To ensure the proper level of fire safety, timely detection of fire, and organized evacuation of people, it is necessary to overhaul the fire alarm system with the installation of a modern warning and evacuation management system

Socio-economic context

Indicator

Value

Number of people who will use the service

890 human

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

School education

Stream

Arrangement of safe conditions in institutions providing general secondary education (fire protection)

Strategic document

Стратегія розвитку територіальної громади

Task

A.1. GOAL A.1: The education system in Drohobych is capable of providing a solid basic education

Project objectives

Project objectives were not specified by the initiator

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Використано державні будівельні норми (ДБН В.2.5-56:2014 «Системи протипожежного захисту»), Правила пожежної безпеки в Україні та приписи ДСНС щодо обов’язковості встановлення систем автоматичного протипожежного захисту в закладах освіти.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
890 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Economic analysis of DNL Lepkoy.docx
03.04.2026
12:31:24 UTC

Alternative technical solutions

Technical Solution 1

Major repairs of the fire alarm system in the premises of the Drohobych Scientific Lyceum named after Bohdan Lepky of the Drohobych City Council, Lviv region at the address: 19 B. Lepky St., Drohobych, Lviv region (Installation of a fire protection system)

Technical Solution 2

Modernization of the fire safety system using innovative energy efficiency and barrier-free technologies

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)1'560'000 UAH7'500'000 UAH
For preparation30'000 UAH500'000 UAH
For implementation1'530'000 UAH7'000'000 UAH
Project operation and closure cost55'000 UAH650'000 UAH
For operation54'000 UAH500'000 UAH
For closing1'000 UAH150'000 UAH
Average annual costs54'000 UAH0 UAH
Project duration, incl.7 months14 months
Deadline for developing a FFS2 months2 months
Implementation period5 months12 months
Service life120 months120 months
Target indicatorsDefined Not defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Pending

[The project initiator has not taken any decision about this alternative technical approach.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, only national

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget1'615'000 UAH8'150'000 UAH
Project cost (preparation and implementation)1'560'000 UAH7'500'000 UAH
For preparation30'000 UAH500'000 UAH
For implementation1'530'000 UAH7'000'000 UAH
Project operation and closure cost55'000 UAH650'000 UAH
For operation54'000 UAH500'000 UAH
For closing1'000 UAH150'000 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service Unitсередня вартість на одного отримувача послуг
Service Unit Cost1'815 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Not applicable – the project does not provide for the provision of paid services or the establishment of tariffs

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds0 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
The project does not fall under the PPP format by its nature/character

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
None of the options are applicable
Does the team have experience implementing similar projects?
No, this is the first project of its kind.

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
No, I need help.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Market riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

Finalization of existing documentation for the preparation of a preliminary feasibility study
[Response was provided in the Investment Feasibility Study]
Updating existing documentation regarding the preparation of the feasibility study
[Response was provided in the Investment Feasibility Study]

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
03/04/2026SP-L-030426-08E60889Community SPInvestment Feasibility StudyIncludeApproved for inclusion in the sector portfolio-
07/04/2026SPP-L-070426-A878312BCommunity SPPInvestment Feasibility StudyInclude--