Major repairs of the power supply system (installation of solar panels) of Mukachevo Preschool Education Institution No. 1 of the Mukachevo City Council of the Transcarpathian region at the address: Mukachevo, Mytropolyta Volodymyra St., 10


Sector
Education and science
Stream
Modernization of energy supply infrastructure for preschool educational institutions
Maturity level
76
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
Local level of SPP
Implementation
Completion

General information

Description of the project

The project involves a major overhaul of the power supply system of Mukachevo Preschool Education Institution No. 1 at the address: Mukachevo, Mytropolyta Volodymyra St., 10, with the installation of solar panels on the roof of the building. The building is two-story with a hip roof, on which 88 HI-MO6 LR8-66HGD 610M solar panels with a capacity of 610 W each will be mounted, with a total capacity of 53.68 kW (per panel) and 50 kW (per inverter). The system includes a SUN-50KSG01HP3-EU-BM4 inverter with a rated output of 50 kW and a switchboard for connecting the power plant. All electrical solutions comply with the requirements of current regulations, taking into account safety, fire and sanitary and hygienic rules. The purpose of the project — ensuring a reliable and environmentally friendly power supply to the institution through the use of renewable solar energy, which will reduce the consumption of traditional electricity and increase the autonomy of the institution. The installation of solar panels will be carried out by a specialized construction organization in compliance with all necessary norms and standards. 

The purpose of the project

Main Goal:

Introducing innovations and energy-efficient solutions

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

The goal of the project is to achieve energy autonomy of the institution by creating its own solar power plant with a capacity of about 53.68 kW. This will ensure uninterrupted and environmentally friendly electricity supply, reduce electricity costs, increase energy efficiency and ensure long-term savings. Methods of achieving the goal: Installation of 88 high-performance Longi LR8-66HGD 610M solar panels on the roof of the building with an appropriate angle of inclination for maximum solar energy collection. Use of inverters to convert direct current into alternating current suitable for consumption in the institution. Ensuring safe installation in compliance with regulatory requirements, fire safety, labor protection. Implementation of a modern energy consumption accounting and management system. Educational activities for staff and the community on the benefits of renewable energy and energy efficiency. Justification of the gap between the current state and the target level: Currently, the institution uses electricity from the general city network, which does not provide independence from interruptions, has significant costs and dependence on tariffs. The lack of its own generating source leads to high operating costs and environmental burden. Installation of solar panels will eliminate this gap by creating its own renewable power, reduce financial burdens, increase resilience to interruptions in the city network, and also improve the environmental situation. This will allow the institution to raise to a modern level of energy efficiency and sustainable development, meeting the requirements of modern public investment projects in the field of education and ecology.

Problems and solutions resulting from project implementation

Key issues: Lack of energy autonomy and dependence on an unstable city power grid with frequent outages, which creates risks for the continuity of the institution's operations. This is especially relevant in the context of military operations and the energy crisis in Ukraine in 2024-2025. High electricity costs and the inability to control these costs due to the lack of its own generation source. Due to dependence on external suppliers and the wear and tear of the system, the likelihood of emergencies and downtime increases. The use of traditional energy sources negatively affects the environment and does not meet the modern challenges of sustainable development. Positive changes from the implementation of the project: Ensuring stable and uninterrupted power supply thanks to its own solar power plant. Reducing electricity costs and increasing energy efficiency. Increasing environmental safety through the use of renewable energy. Increasing the overall resilience of the institution to external factors, including hostilities and crisis situations. Formation of a positive image and implementation of innovative technologies in the field of education.

Socio-economic context

Indicator

Value

Other social

88 equip. units

Strategic Case

Strategic feasibility of the project

Sector

Education and science

Subsector

Preschool education

Stream

Modernization of energy supply infrastructure for preschool educational institutions

Strategic document

Стратегія розвитку територіальної громади

Task

3.4.1 Improving the efficiency of the network of educational institutions and the quality of educational services

Project objectives

Indicator
Base value
Target value
Installation of solar panels
0 equip. units
88 equip. units

Project Sustainable Development Goals

Demand for the service and its dynamics

What methodology was used to estimate demand?

Прогнозування попиту з урахуванням майбутніх змін — враховується розширення закладу, впровадження енергозберігаючих технологій, підвищення рівня автоматизації, зміна кліматичних умов, а також очікуваний ефект від встановлення сонячних панелей.
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
25
95000 kW
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

Climate change adaptation
[Response was provided in the Preliminary Investment Feasibility Study]
Pollution prevention and control
[Response was provided in the Preliminary Investment Feasibility Study]
Protecting and restoring biodiversity and ecosystems
[Response was provided in the Preliminary Investment Feasibility Study]

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Does the project provide for improving women's access to services?

Not applicable to my project
[Response was provided in the Preliminary Investment Feasibility Study]

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
Expert report 1.pdf
02.03.2026
18:18:54 UTC

Alternative technical solutions

Technical Solution 1

Major repairs of the power supply system (installation of solar panels) of Mukachevo Preschool Education Institution No. 1 of the Mukachevo City Council of the Transcarpathian region at the address: Mukachevo, Mytropolyta Volodymyra St., 10

Technical Solution 2

Replacement of the power supply system (installation of solar panels) of Mukachevo Preschool Education Institution No. 1 of the Mukachevo City Council of the Transcarpathian region at the address: Mukachevo, Mytropolyta Volodymyra St., 10

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)2'397'360 UAH2'397'360 UAH
For preparation72'329 UAH72'329 UAH
For implementation2'325'031 UAH2'325'031 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Average annual costs12'000 UAH0 UAH
Project duration, incl.10 months10 months
Deadline for developing a FFS2 months2 months
Implementation period8 months8 months
Service life300 months300 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
0
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
Yes

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget2'397'362 UAH2'397'362 UAH
Project cost (preparation and implementation)2'397'360 UAH2'397'360 UAH
For preparation72'329 UAH72'329 UAH
For implementation2'325'031 UAH2'325'031 UAH
Project operation and closure cost2 UAH2 UAH
For operation1 UAH1 UAH
For closing1 UAH1 UAH
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Preliminary Investment Feasibility Study]
Were the methodological recommendations approved by the Ministry of Finance of Ukraine applied when calculating the indicative budget?
Yes
[Response was provided in the Investment Feasibility Study]

Average project cost per service recipient

Service UnitСередня вартість
Service Unit Cost12'000 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
Partial – the analysis was conducted only for certain groups of consumers or part of the services

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds2'397'360 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
Strategic justification - analysis of the strategic feasibility of the project

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - economic analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - communication with stakeholders

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - risk management

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - social and gender analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - public consultations

[Response was provided in the Preliminary Investment Feasibility Study]

Economic feasibility study - technical expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of available procurement options

[Response was provided in the Preliminary Investment Feasibility Study]

Project management - legal support

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - SDG compliance analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Financial analysis - financial analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Strategic rationale - demand analysis

[Response was provided in the Preliminary Investment Feasibility Study]

Economic justification - environmental expertise

[Response was provided in the Preliminary Investment Feasibility Study]

Business case - analysis of the market environment

[Response was provided in the Preliminary Investment Feasibility Study]

Does the team have experience implementing similar projects?
Partially, we have limited experience

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
Partially, we are considering options

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Economic riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
02/03/2026SP-L-020326-8EB5A754Community SPInvestment Feasibility StudyInclude--
23/03/2026SPP-L-230326-8D3BD9BECommunity SPPInvestment Feasibility StudyInclude-76