Construction of a water tower in the Obukhiv district of the city of Boguslav, Kyiv region


Sector
Municipal infrastructure and services
Stream
Restoration, development and modernization of centralized water supply and wastewater infrastructure, with the introduction of alternative energy sources
Maturity level
73
Preliminary Investment Feasibility Study
Project Status
Investment Feasibility Study
Entry into Portfolio
State level of SP
Implementation
Completion

General information

Description of the project

Ensuring a stable and uniform water supply for the city/village. Increasing water pressure in the network, especially in remote areas. Ensuring a water reserve for emergencies (firefighting, emergency repairs). Increasing the reliability and efficiency of the water supply system.

The purpose of the project

Main Goal:

Improving the condition of infrastructure

Secondary Goal:

Increasing compliance with modern standards

Description of the purpose of the project and ways to achieve it

• Stable water pressure for all consumers. • Water reserve in case of accidents and fires. • Use of modern technologies and energy-efficient equipment. • Reduction of maintenance costs of old tanks. • Improvement of the ecological condition of the network through stable operation of the system.

Problems and solutions resulting from project implementation

Insufficient water pressure in upper and remote areas. Limited water supply for emergencies and firefighting. High water consumption due to old pipes and network losses. Frequent accidents and the need for routine repairs

Socio-economic context

Indicator

Value

Number of people who will use the service

3000 human

Strategic Case

Strategic feasibility of the project

Sector

Municipal infrastructure and services

Subsector

Water supply and sanitation

Stream

Restoration, development and modernization of centralized water supply and wastewater infrastructure, with the introduction of alternative energy sources

Strategic document

Стратегія розвитку територіальної громади

Task

2.1.2 Modernization of water supply, sewage, and heating and water supply with the introduction of alternative energy sources

Project objectives

Indicator
Base value
Target value
Construction of a water tower
1 units
1 units

Demand for the service and its dynamics

What methodology was used to estimate demand?

Підхід до реалізації Проєкт передбачає використання системного підходу, що включає інженерно-технічний аналіз, фінансово-економічну оцінку та управління ризиками. Основна методологія базується на: вимогах ДБН та СНиП щодо проєктування водонапірних споруд; принципах державно-приватного партнерства (ДПП) у разі залучення інвестицій; міжнародних стандартах управління інфраструктурними проєктами (PMI, PRINCE2).
[Response was provided in the Preliminary Investment Feasibility Study]

Has data from external sources been used in the demand assessment?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Does the demand forecast take into account the latest demographic and economic forecasts?

No
[Response was provided in the Preliminary Investment Feasibility Study]
Indicator
Year
Demand
Annual demand for services/infrastructure
1
3000 human
Economic justification

Analysis of the project's impact on ecology and climate change

Does the planned activity have a potential positive contribution to achieving climate or environmental objectives?

None of the options are applicable

Is the proposed project expected to significantly harm any of the following climate or environmental objectives?

None of the options are applicable

Project sustainability and inclusivity

Identify potential gender risks of the project and indicate possible ways to overcome them:

None of the options are applicable

Does the project provide for improving women's access to services?

None of the options are applicable

Are civil society organizations representing women and vulnerable groups included in the consultation process?

No
[Response was provided in the Preliminary Investment Feasibility Study]

Documents

Name
Date
social.docx
01.10.2025
13:27:40 UTC

Alternative technical solutions

Technical Solution 1

Construction of a pressure tower

Technical Solution 2

Current repairs

Cost breakdownCost justificationCost justification
Project cost (preparation and implementation)3'500'000 UAH1'200'000 UAH
For preparation500'000 UAH400'000 UAH
For implementation3'000'000 UAH800'000 UAH
Project operation and closure cost4'500'000 UAH800'000 UAH
For operation3'500'000 UAH500'000 UAH
For closing1'000'000 UAH300'000 UAH
Average annual costs8'000'000 UAH0 UAH
Project duration, incl.24 months24 months
Deadline for developing a FFS12 months12 months
Implementation period12 months12 months
Service life12 months12 months
Target indicatorsDefined Defined
Technical Solution Status
Active

[The technical approach was selected for further detailed analysis or implementation.]

Rejected

[The technical approach was not selected for further detailed analysis or implementation.]

Components of a technical solution
To components
1
To components
0

Commercial Justification

Supplier and contractor market assessment

Is the project likely to attract a sufficient number of bidders to ensure real competition that will encourage bidders to think innovatively and maximize the quality of their proposals?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Is the project of interest to small and medium-sized enterprises?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Will the project involve national or international suppliers and contractors?
Yes, both national and international

[Response was provided in the Preliminary Investment Feasibility Study]

Has an analysis of available procurement options been conducted for the technical solution?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Financial justification

Total project budget

Total preliminary budget8'000'000 UAH2'000'000 UAH
Project cost (preparation and implementation)3'500'000 UAH1'200'000 UAH
For preparation500'000 UAH400'000 UAH
For implementation3'000'000 UAH800'000 UAH
Project operation and closure cost4'500'000 UAH800'000 UAH
For operation3'500'000 UAH500'000 UAH
For closing1'000'000 UAH300'000 UAH
Чи була під час уточнення орієнтовного бюджету використана Методика розрахунку вартості публічного інвестиційного проєкту, затверджена наказом Міністерства фінансів України №316 від 23.06.2025 р.?
No
[Response was provided in the Investment Feasibility Study]
Чи була під час розрахунку орієнтовного бюджету використана Методика розрахунку вартості публічного інвестиційного проєкту, затверджена наказом Міністерства фінансів України №316 від 23.06.2025 р.?
No
[Response was provided in the Preliminary Investment Feasibility Study]

Average project cost per service recipient

Service UnitБудівництво водонапірної башти
Service Unit Cost8'000'000 UAH

Profitability of the project

Is the project expected to generate income?NoNo

Availability of services

Has an analysis been conducted of the accessibility of services for consumers and their financial ability to pay the established tariffs?
No – analysis not performed

[Response was provided in the Preliminary Investment Feasibility Study]

Project Financing Mechanisms

Are funding sources and mechanisms identified?

Source and MechanismYesNo

Funding Sources

Approved Funds0 UAH0 UAH
Expected Funds8'000'000 UAH0 UAH

Public-private partnership

Has a qualitative and quantitative assessment of the project's suitability for implementation through a PPP mechanism been conducted?
No, no assessment was conducted.

[Response was provided in the Preliminary Investment Feasibility Study]

Are there, after conducting an appropriate study, private investors interested in the possibility of implementing the project in the PPP format?
No

[Response was provided in the Preliminary Investment Feasibility Study]

Management Rationale

Team competencies

Determine which competencies/expertise required for successful project preparation and implementation can be provided by the project initiator's own project team (without involving external advisors)
None of the options are applicable
Does the team have experience implementing similar projects?
No, this is the first project of its kind.

[Response was provided in the Preliminary Investment Feasibility Study]

Identify which competencies/expertise required for successful project preparation and implementation need to be strengthened by engaging independent experts or consultants
None of the options are applicable
Is there an understanding of where to find relevant experts and consultants?
No, I need help.

[Response was provided in the Preliminary Investment Feasibility Study]

Risk assessment

Financial riskDefinedUndefined
Results of the feasibility analysis
Project Preparation Program Engagement and Funding Needs

Does the project require additional preparation assistance from Project Preparation Facilities (PPF)?

None of the options are applicable

Project Approval History

DateDecision NumberPortfolioProject StatusDecisionReasonsMaturity level
08/10/2025SP-L-081025-9C0F303DCommunity SPInvestment Feasibility StudyInclude--
22/03/2026SP-N-220326-4AC70647State SPInvestment Feasibility StudyInclude--
27/11/2025SPP-L-271125-CF8A7F6BCommunity SPPInvestment Feasibility StudyInclude-73