The purpose of the project:
Infrastructure improvement
Key spending unit
State Agency for Reconstruction and Development of Infrastructure of Ukraine
Functional classification of expenditures and budget crediting
0451 - Автомобільний транспорт
Target priority of the government
010602 - Розвиток транспортної інфраструктури
Score
4.9125
Basic data
Problems
Current status, description of problems and needs for their solution
Contractors "Doğuş" and "Onur Group" insist on receiving a 30% advance from Citibank N.A. financing for the execution of the British component. UK suppliers require 100% advance payment.
The need to amend the Resolution of the CMU of July 28, 2023 No. 790 to ensure sustainable financing.
A detailed description of the project goal and the way to achieve it
Bridges/highways in the Kyiv region were destroyed as a result of the Russian invasion. Implementation of the project will allow them to be restored.
Coordination of the project with strategic documents
Another regulatory document
Budget Declaration 2024-2025, in Appendix 1 to the Budget Declaration "Limited indicators of expenditures and granting of credits from the state budget and goals of state policy in the relevant field of activity and indicators of their achievement in 2023 — 2027" in the Section "Goals of state policy in the relevant field of activity" , the formation and/or implementation of which is ensured by the chief administrator of state budget funds, and the indicators of their achievement" for the Agency are defined in paragraph 1 "1. Ensuring the improvement of the state of the public road network, its effective functioning and development"
Priority action plan of the governmentCabinet of Ministers of Ukraine Order No. 137 of February 16, 2024
Demand for the service and its dynamics
Category
Year
Rating
Measure
Project indicators
Indicator
Base value
Target value
Number of jobs, including for IDPs
1
1
Bandwidth
10
1000
Risk assessment
Risk
Category
Degree
Probability
Strategy
The impact of military operations on the implementation of the project
Other risk
Considerable
Low
Acceptance
Untimely receipt of funds to the main manager of funds and executor from the State budget
Financial risk
Critical
Medium
Reduction
Project plan
Budgeting
Implementation
Preparation
Technical design
Feasibility study
Assessment
Financing
763 days
751 days
227 days
184 days
94 days
74 days
0 days